Mixed-use development with in-fill affordable housing - Cecil Avenue and Roger Avenue, Castle Hill
610 apartments in towers at Cecil Avenue, Castle Hill
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its SSD78156221 - Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
610 apartments in towers at Cecil Avenue, Castle Hill
The proponent proposes to demolish the existing buildings at 93-107 Cecil Avenue and 9-10 Roger Avenue, Castle Hill, in The Hills Shire, and build a mixed-use development in stages. It would have 610 apartments, 117 of them affordable apartments, and 3,789 m² of commercial floor space. The buildings would range from 23 to 35 storeys. No capital investment or job numbers are stated.
The environmental impact statement (EIS) is dated March 2025. A notice of re-exhibition was issued in March 2026, and the proponent lodged a response to submissions in June 2026. The project drew 35 submissions: 25 objecting, 3 supporting and 7 commenting. The case is now at "More Information Required", and a request for additional information is on file. Next, the proponent supplies that information, the department finishes its assessment, and a decision follows.
- Apartments
- 610 dwellingsPortal page
- Affordable apartments
- 117 dwellingsPortal page
- Commercial floor space
- 3,789 m²Portal page
- Maximum building height
- 35 storeysPortal page
- Minimum building height
- 23 storeysPortal page
The department's description
Demolition of existing buildings and staged construction of a mixed-use development comprising3,789 square metres of commercial floor space and 610 apartments (117 affordable apartments). The development ranges from 23 to 35 storey buildings.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
35 submissions: 29 from the public, 2 from organisations and 4 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
134 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
EIS51
- Appendix 10_Preliminary Geotechnical Report
- Appendix 11_Traffic and Parking Asessment Report
- Appendix 12_Noise Impact Assessment
- Appendix 13_BCA Compliance Assessment Report
- Appendix 14_BASIX
- Appendix 15_Operational Waste Management Plan
- Appendix 16_C&D Waste Management Plan
- Appendix 17_Arboricultural Impact Assessment
- Appendix 18_Accessibility Report
- Appendix 19_Civil Design
- Appendix 1_SSD SEARs and Cover Letter
- Appendix 20_Water Management Report
- Appendix 21_Overland Flow Assessment
- Appendix 23_Connecting with Country Report
- Appendix 24_Archaeological Assessment
- Appendix 25_Statement of Heritage Impact
- Appendix 26_Aboriginal Curltural Heritage Report
- Appendix 27_Biodiversity Assessment Report and Waiver
- Appendix 28_Employment Estimate
- Appendix 29_Social Impact Assessment
- Appendix 2_Sears Compliance Table
- Appendix 30_Community Engagement Report
- Appendix 31_Pedestrian Wind Environment Assessment
- Appendix 32_Infrastructure Delivery Plan
- Appendix 33_Community Housing Provider Letter
- Appendix 34_CPTED Assessment
- Appendix 35_Acid Sulfate Soils Management Plan
- Appendix 36_HAZMAT
- Appendix 37_Salinity Management Plan
- Appendix 38_Visual Impact Assessment
- Appendix 39_CN&V Management Plan
- Appendix 3_Statutory Compliance Table
- Appendix 40_Construction Traffic Management Plan
- Appendix 41_Green Travel Plan
- Appendix 42_Clause 4.6 request_Clause 7.18 of THLEP
- Appendix 43_Civil and Public Domain Report
- Appendix 44_Stormwater Management Plan
- Appendix 45_ESD Report
- Appendix 46_Embodied Emissions Materials
- Appendix 47_Lift Capacity
- Appendix 48_ConsolidatedModel_A.sqz
- Appendix 49_Model_.drn
- Appendix 4_Mitigation Measures Table
- Appendix 5_Survey Plan
- Appendix 6_Architectural Package
- Appendix 7_Design Report
- Appendix 7_Design Verification Statement
- Appendix 8_Landscape
- Appendix 9_Preliminary Site Investigation
- Application Form
- SSD78156221 - Environmental Impact Statement
Response to Submissions14
- Appendix 10_Structural Statement
- Appendix 11_FIood Impact and Risk Assessment
- Appendix 12_BDAR Waiver
- Appendix 2_Updated Mitigation Measures Table
- Appendix 3_Amended Architectural Package
- Appendix 4_Amended Landscape Plans and Design Report
- Appendix 5_Amended Visual Impact Assessment
- Appendix 6_Employment Estimate
- Appendix 7_Community Housing Provider Letter
- Appendix 8_Lift Capacity Letter
- Appendix 9_NatHERS Certificates
- Request RTS Letter
- Request RTS Letter cecil
- Response to Submissions Report (June 2026)
Agency Advice14
- CPHR Response - EIS
- CPHR Response - SAR
- Council Submission - EIS
- Council Submission - SAR
- DCCEEW Water Response - EIS
- DCCEEW Water Response - SAR
- Endeavour Energy Advice - EIS
- Endeavour Energy Advice - SAR
- HNSW ACH Response - SAR
- Heritage NSW Response - EIS
- Sydney Water Response - EIS
- Sydney Water Response -SAR
- TfNSW Response - EIS
- TfNSW Response - SAR
Amendments42
- Amended Application_20260313004618
- Amendment Acceptance Letter
- Appendix 10_Traffic and Parking Assessment Report
- Appendix 11_Noise Impact Assessment
- Appendix 12_BASIX Certificates
- Appendix 13_Operational Waste Management Plan
- Appendix 14_Accessibility Report
- Appendix 15_Civil Design
- Appendix 16_Water Management Report
- Appendix 17_Flood Risk Assessment
- Appendix 18_EDC Report
- Appendix 19_Connecting with Country Report
- Appendix 2 - Updated Statutory Compliance Table
- Appendix 20_Statement of Heritage Impact
- Appendix 21_Natural Ventilation Study
- Appendix 22_CPTED Assessment
- Appendix 23_Visual Impact Assessment
- Appendix 24_CN&V Management Plan
- Appendix 25_Green Travel Plan
- Appendix 26_Clause 4.6 request - Clause 7.18 of THLEP
- Appendix 27_Civil and Public Domain Report
- Appendix 28_Stormwater Management Plan
- Appendix 29_ESD Report
- Appendix 30_Embodied Emissions Materials
- Appendix 31_ConsolidatedModel_A.sqz
- Appendix 32_Model_.drn
- Appendix 33_Clause 4.6 request - building height
- Appendix 34_Market and Economic Assessment
- Appendix 35_Employment Estimate
- Appendix 36_ACHAR
- Appendix 37_Groundwater Seepage Analysis Report
- Appendix 38_Pedestrian Level Wind - Wind Tunnel Test
- Appendix 39_Development Capacity Study
- Appendix 3_Updated Mitigation Measures Table
- Appendix 40_Arboricultural Report
- Appendix 4_Site Consolidation Plan, Section 88B Instruments
- Appendix 5_Architectural Package
- Appendix 6_Design Verification Statement and Design Report
- Appendix 7_Landscape Plans and Design Report
- Appendix 8_Detailed Site Investigation
- Appendix 9_Geotechnical Investigation
- Submissions and Amendment Report
Additional Information9
- Appendix 11_Amended Flood Impact and Risk Assessment
- Appendix 13_Amended Stormwater Management Plan
- Appendix 14_Amended DRAINS Model
- Appendix 15_HECRAS Model
- Appendix 16_Groundwater Seepage Analysis
- Appendix 17_Response to DCCEEW Water
- Appendix 3_Amended Architectural Drawings
- Appendix 4_Amended Landscape Plans and Design Report
- Request for Additional Information
What's near it
Where it is
- Suburb
- Castle Hill
- Council area
- The Hills Shire
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.