Mixed use development with in-fill affordable housing - 21 Auburn Street, Wollongong
A 160-apartment tower at 21 Auburn Street, Wollongong
Where it is in the process
At response to submissions
What it proposes
AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 160-apartment tower at 21 Auburn Street, Wollongong
The proponent proposes to demolish the existing buildings at 21 Auburn Street, Wollongong, in the Wollongong City Council area, and build a shop-top housing tower with 160 apartments, 30 of them affordable housing. It would stand 77.62 m high and have 27 storeys. There would be 386.37 m² of ground floor commercial and retail space and four basement levels with 177 car parking spaces. The estimated development cost is $70,688,023, with about 185 construction jobs and about 10 operational jobs.
The environmental impact statement (EIS) is dated 17 August 2026. The project is at the response to submissions stage and has drawn 8 submissions: 6 objecting, 1 supporting and 1 commenting. Next, the proponent responds to the submissions and may amend the project. The department then assesses it and a decision follows. No exhibition dates are given.
- Estimated development cost
- $70.7MEnvironmental Impact Statement
- Apartments
- 160 dwellingsEnvironmental Impact Statement
- Affordable housing units
- 30 dwellingsEnvironmental Impact Statement
- Maximum building height
- 77.62 mEnvironmental Impact Statement
- Building storeys
- 27 storeysEnvironmental Impact Statement
- Commercial and retail floor area
- 386.37 m²Environmental Impact Statement
- Car parking spaces
- 177 car spacesEnvironmental Impact Statement
- Construction jobs
- 185 jobsEnvironmental Impact Statement
The department's description
Mixed use development with in-fill affordable housing, 21 Auburn Street Wollongong.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
8 submissions: 7 from the public and 1 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
69 documents in 5 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs2
EIS62
- Appendix 1 SEARS table
- Appendix 10 Design Report
- Appendix 11 Solar Light Reflectivity Study
- Appendix 12 Visual Impact Assessment
- Appendix 12a Visual Impact Assessment - Appendix A
- Appendix 13 Apartment Design Guide Compliance Assessment
- Appendix 14 Noise and Vibration Impact Assessment
- Appendix 15 Survey Plan
- Appendix 16 Connecting with Country
- Appendix 17 Flood Impact Study
- Appendix 18 Geotechnical Investigation Report
- Appendix 19 Detailed Site Investigation
- Appendix 2 Statutory Compliance Table
- Appendix 20 Remediation Action Plan
- Appendix 21 BDAR Waiver Request
- Appendix 22 BDAR Waiver
- Appendix 23 Aboriginal Cultural Heritage Assessment
- Appendix 23a Aboriginal Cultural Heritage Assessment
- Appendix 24 Statement of Heritage Impact
- Appendix 25 Community Housing Provider Letter
- Appendix 26 Hazardous Materials Survey
- Appendix 27 Landscape Design Report
- Appendix 28 Architectural Drawing Package 20260819
- Appendix 29 Landscape Plans
- Appendix 3 Community Engagement Report
- Appendix 30 Traffic Drawings Set
- Appendix 31 Construction Traffic Management Plan
- Appendix 32 Operational Waste Management Plan
- Appendix 33 Utility and Infrastructure Management Plan
- Appendix 33a Padmount Substation Earthing Diagram
- Appendix 34 Stormwater Treatment Train Report
- Appendix 35 Stormwater Civils Set
- Appendix 36 Housing SEPP Principles
- Appendix 37 BASIX Certificate
- Appendix 38 ESD Report
- Appendix 39 Traffic and Parking Impact Assessment
- Appendix 4 Mitigation Measures
- Appendix 40 Design Excellence Report
- Appendix 41 Access Report
- Appendix 42 BCA Compliance Report
- Appendix 43 Clause 4.6
- Appendix 44 Green Travel Plan
- Appendix 45 Dewatering Managment Plan
- Appendix 47 Section J Report
- Appendix 48 Aviation Report
- Appendix 49 BASIX Stamped Plans
- Appendix 50 Pedestrian Wind Assessment
- Appendix 51 Arboriculutral Impact Assessment Report
- Appendix 52 Cut and Fill Plan
- Appendix 53 Surface and Groundwater Impact Assessment
- Appendix 54 Historical Archaeological Assessment
- Appendix 55 PreDA Feedback
- Appendix 56 Electrical Infrastructure Assessment
- Appendix 57 Electrical Infrastructure Design Certification
- Appendix 58 NatHERS Certificate
- Appendix 59 SDRP Response Table
- Appendix 6 Authorisation to lodge
- Appendix 60 Soil Erosion and Sedimentation Drawings
- Appendix 61 88b Instrument
- Appendix 8 Social Impact Assessment
- Appendix 9 Crime Prevention Report
- Environmental Impact Statement
What's near it
Where it is
- Suburb
- Wollongong
- Council area
- Wollongong
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.