On the map
State significant development

Mixed use development & Concurrent rezoning 209 Railway Terrace Schofields

480 homes in four towers at 209 Railway Terrace, Schofields

Under way: at response to submissionsHomesDistrict scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

480 homes in four towers at 209 Railway Terrace, Schofields

The proponent proposes a mixed use development at 209 Railway Terrace, Schofields, in the Blacktown council area. The portal describes 480 residential units over four towers, with 15% affordable housing, a neighbourhood retail centre and a childcare centre. The environmental impact statement (EIS) describes it as shop top housing with a gym, childcare, retail tenancies and a supermarket. It is lodged with a concurrent rezoning of the land. No capital investment is stated.

The EIS is dated 20 Aug 2026. It drew 15 submissions: 10 objecting, 3 supporting and 2 commenting. The case is now at the response to submissions stage, where the proponent responds to the issues raised and may amend the project. The department then assesses it and prepares an assessment report. A decision follows. Each stage has its own date, but none is given here.

Residential units
480 dwellingsPortal page
Affordable housing share
15%Portal page
Towers
4 towersPortal page
Public submissions
15 submissionsPortal page
Submissions objecting
10 submissionsPortal page

The department's description

Mixed use development including a neighbourhood retail centre, childcare centre and 480 residential units over four towers, with 15% affordable housing.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

15 submissions: 13 from the public, 1 from organisations and 1 from public authorities

Object10
Support3
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

59 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation1
Request for SEARs3
SEARs3
EIS45
Response to Submissions1
Agency Advice5

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.