On the map
Part 3A project

Meadowbank Residential

Decided: approved on 6 Mar 2013Homes

Where it is in the process

Approved on 6 Mar 2013

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination6 Mar 2013 (done)
  10. Approved6 Mar 2013

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Meadowbank Residential MOD 2 - SubdivisionMP09_0219-Mod-2

Decided: approved on 13 Apr 2015 by the department (director)

/

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application6

See the 6 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Meadowbank Residential MOD 1 - Design ChangesMP09_0219-Mod-1

Decided: approved on 16 Oct 2014 by the Independent Planning Commission · 59 submissions

/

Its 23 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.