On the map
State significant development

McPhillamys Gold Project

Decided: approved on 30 Mar 2023Mining

Where it is in the process

Approved on 30 Mar 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination30 Mar 2023 (done)
  9. Approved30 Mar 2023

What it proposes

The department's description

Development of an open cut mine and water supply pipeline.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

671 submissions: 624 from the public, 27 from organisations and 20 from public authorities

Object397
Support218
Comment56

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 - Layout OptimisationSSD-9505-Mod-1

Withdrawn: withdrawn

Layout changes to optimise the project’s construction and operation and incorporate the 132 kV electricity transmission line into the project.

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Early Consultation2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.