Mayfield Fuel Facility

Decided: approved on 8 Jun 2012Industry and warehouses

Where it is in the process

Approved on 8 Jun 2012

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination8 Jun 2012 (done)
  10. Approved8 Jun 2012

What it proposes

The department's description

Mayfield Fuel

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 4 from the public

Object4
Support0
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Mayfield Fuel MOD 3 - Increase ThroughputMP08_0130-Mod-3

Decided: approved on 10 Jul 2014 by the department (director)

/

Its 9 documents

Its page on the Planning Portal

Mod 2 - Health Risk ConsultationMP08_0130-Mod-2

Decided: approved on 28 Nov 2013 by the department (director)

Its page on the Planning Portal

Mod 1 - Additional TanksMP08_0130-Mod-1

Decided: approved with conditions on 26 Jul 2013 by the department (executive director)

Its 15 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.