State significant development

Maxwell Solar Farm

Decided: approved on 19 Aug 2020Energy: solarNeighbourhood scale

Where it is in the process

Approved on 19 Aug 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination19 Aug 2020 (done)
  9. Approved19 Aug 2020

What it proposes

The department's description

Development of a 25 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

14 submissions: 2 from the public and 12 from public authorities

Object0
Support3
Comment11

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Maxwell Solar Farm - Modification 1SSD-9820-Mod-1

Under way: at prepare mod report

Increase to the generational capacity to 100 MW and alternative connection point.

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.