On the map
State significant development

Marsden Park Data Centre

A 504 MW data centre at Hollinsworth Road, Marsden Park

Decided: approved on 27 Nov 2025Data centresRegional scale

Where it is in the process

Approved on 27 Nov 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination27 Nov 2025 (done)
  9. Approved27 Nov 2025

What it proposes

AI summary. Written from this project's page and its Signed - SSD Instrument of Determination and Signed - SSD-SSI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 504 MW data centre at Hollinsworth Road, Marsden Park

The project is a data centre campus at 105 and 113 Hollinsworth Road, Marsden Park, in the Blacktown council area, on a site of 20.91 ha. It has six four-storey data centre buildings, up to 37.515 m high, with 504 MW of IT load and a 720 MW power capacity. It includes a substation, 240 back-up diesel generators and 265 car spaces. The estimated cost is $3,113,226,273, with up to 220 construction jobs and 265 operational jobs.

The environmental impact statement was exhibited from 14 Nov 2024 to 11 Dec 2024 and drew 4 submissions: 2 objecting, 1 supporting and 1 commenting. The council withdrew its objection after changes to the design. The department's assessment, of November 2025, found it approvable, and a director of the department approved it on 27 Nov 2025 as delegate of the Independent Planning Commission. Next, the proponent must meet the consent's conditions before and during construction.

Estimated development cost
$3.11bnSigned - SSD-SSI Assessment Report
Data centre IT load
504 MWSigned - SSD-SSI Assessment Report
Maximum power capacity
720 MWSigned - SSD-SSI Assessment Report
Construction jobs
220 jobsSigned - SSD-SSI Assessment Report
Operational jobs
265 jobsSigned - SSD-SSI Assessment Report
Maximum building height
37.52 mSigned - SSD-SSI Assessment Report
Site area
20.91 haSigned - SSD-SSI Assessment Report
Back-up diesel generators
240 generatorsSigned - SSD-SSI Assessment Report

The department's description

Construction and operation of a data centre with a power consumption of 504 megawatts (MW), comprising of six, four storey data centre buildings, a 720 MW substation, associated hardstand, car parking and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 1 from the public, 1 from organisations and 2 from public authorities

Object2
Support1
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Marsden Park Data Centre Modification 1 - Changes to Site LayoutSSD-70889211-Mod-1

Under way: at assessment

Modifications of site layout including replacing MP4 building with a two-storey administration building, offices and 5 MW data hall, additional level to MP5 and MP6, redistribution of MW load and changes to plant deck and site infrastructure.

Its 17 documents

17 documents in 3 folders, each on the NSW Planning Portal

Modification Application13

See the 13 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

158 documents in 12 folders, each on the NSW Planning Portal

Early Consultation3
Notice of Exhibition1
Request for SEARs2
SEARs4
EIS47
Response to Submissions25
Agency Advice29
Amendments3
Additional Information27
Determination6
Management Plans and Strategies10
Notifications1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.