Marsden Park Data Centre
A 504 MW data centre at Hollinsworth Road, Marsden Park
Where it is in the process
Approved on 27 Nov 2025
What it proposes
AI summary. Written from this project's page and its Signed - SSD Instrument of Determination and Signed - SSD-SSI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 504 MW data centre at Hollinsworth Road, Marsden Park
The project is a data centre campus at 105 and 113 Hollinsworth Road, Marsden Park, in the Blacktown council area, on a site of 20.91 ha. It has six four-storey data centre buildings, up to 37.515 m high, with 504 MW of IT load and a 720 MW power capacity. It includes a substation, 240 back-up diesel generators and 265 car spaces. The estimated cost is $3,113,226,273, with up to 220 construction jobs and 265 operational jobs.
The environmental impact statement was exhibited from 14 Nov 2024 to 11 Dec 2024 and drew 4 submissions: 2 objecting, 1 supporting and 1 commenting. The council withdrew its objection after changes to the design. The department's assessment, of November 2025, found it approvable, and a director of the department approved it on 27 Nov 2025 as delegate of the Independent Planning Commission. Next, the proponent must meet the consent's conditions before and during construction.
- Estimated development cost
- $3.11bnSigned - SSD-SSI Assessment Report
- Data centre IT load
- 504 MWSigned - SSD-SSI Assessment Report
- Maximum power capacity
- 720 MWSigned - SSD-SSI Assessment Report
- Construction jobs
- 220 jobsSigned - SSD-SSI Assessment Report
- Operational jobs
- 265 jobsSigned - SSD-SSI Assessment Report
- Maximum building height
- 37.52 mSigned - SSD-SSI Assessment Report
- Site area
- 20.91 haSigned - SSD-SSI Assessment Report
- Back-up diesel generators
- 240 generatorsSigned - SSD-SSI Assessment Report
The department's description
Construction and operation of a data centre with a power consumption of 504 megawatts (MW), comprising of six, four storey data centre buildings, a 720 MW substation, associated hardstand, car parking and landscaping.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
4 submissions: 1 from the public, 1 from organisations and 2 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Marsden Park Data Centre Modification 1 - Changes to Site LayoutSSD-70889211-Mod-1
Modifications of site layout including replacing MP4 building with a two-storey administration building, offices and 5 MW data hall, additional level to MP5 and MP6, redistribution of MW load and changes to plant deck and site infrastructure.
Its 17 documents
17 documents in 3 folders, each on the NSW Planning Portal
Modification Application13
Agency Advice3
Additional Information1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
158 documents in 12 folders, each on the NSW Planning Portal
Early Consultation3
Notice of Exhibition1
Request for SEARs2
SEARs4
EIS47
- A1 - SEARs Table
- A10 - Accessibility Report
- A11 - Air Quality Impact Assessment
- A12 - Arboricultural Impact Assessment
- A13 - BCA Report
- A14- BDAR Waiver Request
- A15 - Bushfire Report
- A16 - Contamination Report
- A17 - ESD Report
- A18 - Emissions (Greenhouse Gas Assessment)
- A19 - Engagement Report
- A2 - Statutory Compliance Table Hollinsworth
- A20 - Estimated Development Cost Letter
- A21 – Historical Archaeological Assessment
- A22 - Groundwater Impact Assessment
- A23 - Geotechnical Report
- A24 - Preliminary Hazards and Risks Memo
- A25 - Infrastructure and Utilities Report
- A26 – Integrated Water Management Plan
- A26A - Stormwater Data
- A27 - NABERS Embodied Emissions Form
- A28 - Construction Noise and Vibration Report
- A29 - Operational Noise and Vibration Report
- A3 - Mitigation measures - Hollinsworth
- A30 – Statement of Heritage Impact
- A31 – Sydney Water Statement of AP&F
- A32 - Social Impact Assessment
- A33 - Transport Impact Assessment
- A34 - Visual Impact Assessment
- A35 - Waste Management Plan
- A36 - CDC 8591-1
- A37 – Early Works DA-24-00386 Approval
- A38 - 5MW DA Plans
- A39 - BGCDCP 2010 Compliance Assessment
- A4 - Site Survey Plan
- A40A - Easement creation dealing
- A40B - Easement Letter
- A41 - Prescribed Ecological Actions Report
- A42 - GHG Mitigations Plan
- A5 - Architectural Plans
- A6 - Architectural Design Report
- A7 - Landscape Masterplan
- A8 - Civil Drawings
- A9 - Redacted ACHAR
- Application_20241104040014
- Environmental Impact Statement
- NABERS AGreement to Rate
Response to Submissions25
- A1 - Amended Greenhouse Gas Assessment
- A10 - TFNSW Owner's Consent
- A11 - Amended Landscape Plans
- A12 - Preliminary Risk Screening
- A13 - Preliminary Risk Screening Memorandum
- A14 - Validation Report
- A15 - Updated Arboricultural Impact Assessment
- A16 - Site Audit Report
- A17 - Amended Air Quality Impact Assessment
- A18 – Amended ONVIA
- A19 – Amended CNVIA
- A2 - Amended Greenhouse Gas Mitigation Plan
- A20 – Amended Architectural Plans
- A21 – Facade Articulation Design Report
- A22 – Amended Visual Impact Assessment
- A24 - Submissions Register
- A3 - ESD Report
- A4 - Revised BDAR Waiver Request
- A5 - Car Parking Reuse Plan
- A6 - Amended Civil Plans
- A7 - Amended Integrated Water Management Strategy
- A8 - Amended Infrastructure Report
- Department's detailed comments
- Formal RTS Report - 105-113 Hollinsworth Road, Marsden Park
- Request RTS Letter
Agency Advice29
- BDAR - CPHR Advice
- EIS - BCS Response
- EIS - Council Addendum Response
- EIS - Council Response
- EIS - EPA Response
- EIS - FRNSW Response
- EIS - HNSW ACH Response
- EIS - Sydney Water Response
- EIS - TFNSW Response
- EIS - WSLHD Advice
- HNSW ACH - Marsden Park Data Centre - SSD-70889211
- RFI - EPA Advice
- RFI - HNSW ACH Advice
- RTS - CPHR Advice
- RTS - Council Response
- RTS - EPA Advice
- RTS - FRNSW Advice
- RTS - Heritage NSW Advice
- RTS - TfNSW Advice
- RTS - WSLHD Advice
- SEARs - BCS Advice
- SEARs - Council Advice
- SEARs - EPA Advice
- SEARs - Endeavour Energy Advice
- SEARs - FRNSW Advice
- SEARs - HNSW ACH Advice
- SEARs - Sydney Water Advice
- SEARs - TfNSW Advice
- SEARs - WaterNSW Advice
Amendments3
Additional Information27
- A1 - Acoustic Memo
- A1 - BDAR
- A1 - DPHI letter dated 03 July 2025
- A2 - EPA letter dated 03 July 2025
- A3 - Updated ONVIA (clean)
- A3b - Updated ONVIA (TC)
- A4 - Updated ONVIA Memo
- A5 - Register of Updated ONVIA comments
- A6 - Air Quality Memo
- Att 1 - Facade Articulation Design Report
- Att 2 - Updated Architectural Plans
- Att 3 - Amended VIA
- Att 4 - Updated ONVIA
- Att 5 - Updated CNVIA Criteria Response
- Att 6 - Updated AQIA
- Att 7 - AHIP
- Cover Letter BDAR - Marsden Park Data Centre
- Cover Letter_Additional Information
- Final Human Health Impact Assessment
- Patch Cover Letter - Acoustic RFI Response
- Patch Cover Letter - Marsden Park Data Centre
- RFI - Exceedances of the PNTLs during operation
- Request for Additional Information
- Request for Additional Information
- Request for Additional Information
- _CPHR+advice+on+Interim+RTS_
- _EPA+response+-+Marden+Park+Data+Centre+-+SSD-70889211_
Determination6
Management Plans and Strategies10
- Approval of Plan Strategy or Study
- Approval of Plan Strategy or Study - ESCP
- Approval of Staging Request
- Approval of Updated Staging Request
- CEMP Approval Letter
- Construction Environmental Management Plan_Rev 3
- Updated Patch Cover Letter_Staging
- Updated Staging Plan_May 2026
- Updated Staging Request_May 2026
- Vegetation Management Plan
Notifications1
What's near it
Where it is
- Suburb
- Marsden Park
- Council area
- Blacktown
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.