On the map
State significant development

Mangoola Coal Mine

Decided: approved on 7 Jun 2007Mining

Where it is in the process

Approved on 7 Jun 2007

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination7 Jun 2007 (done)
  8. Approved7 Jun 2007

What it proposes

The portal gives no description.

Modifications

8 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 6 - Extraction Rate IncreaseMP06_0014-Mod-6

Decided: approved by the Independent Planning Commission · 45 submissions

Its 108 documents

Its page on the Planning Portal

Mangoola Coal MOD8 - Administrative ModificationMP06_0014-Mod-8

Decided: approved on 14 Jun 2017 by the Independent Planning Commission

/

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mangoola Coal MOD7 - Traffic Noise ManagementMP06_0014-Mod-7

Decided: approved on 22 Aug 2016 by the Independent Planning Commission

/

Its 10 documents

Its page on the Planning Portal

Mod 4 - Modify Approved Mine PlanMP06_0014-Mod-4

Decided: approved on 22 Jun 2012 by the Independent Planning Commission

Its 33 documents

Its page on the Planning Portal

Mod 5 - Night Time WorksMP06_0014-Mod-5

Decided: approved on 23 Feb 2010 by the department (executive director)

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Relocate Mine Infrastructure AreaMP06_0014-Mod-3

Decided: approved on 4 Nov 2009 by the department (executive director)

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 2 - Relocate Water Supply PipelineMP06_0014-Mod-2

Decided: approved on 23 Jun 2009 by the department (deputy director-general)

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 1MP06_0014-Mod-1

Decided: approved on 22 Jul 2008 by the department (executive director)

Its 11 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.