On the map
Part 3A project

Macquarie University - Hospital

Decided: approved on 13 May 2007Health

Where it is in the process

Approved on 13 May 2007

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination13 May 2007 (done)
  10. Approved13 May 2007

What it proposes

The portal gives no description.

Modifications

7 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 7 - Closure Technology PlaceMP06_0172-Mod-7

Decided: approved on 14 Feb 2012 by Dir(Metro)

Its 13 documents

13 documents in 2 folders, each on the NSW Planning Portal

Application11

See the 11 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 6 - SignageMP06_0172-Mod-6

Decided: approved on 22 Feb 2010 by the department (executive director)

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 5 - SubdivisionMP06_0172-Mod-5

Decided: approved on 16 Jun 2009 by the department (executive director)

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA6

See the 6 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 4 - Fitout & Internal WorksMP06_0172-Mod-4

Decided: approved on 15 Jun 2009 by the department (executive director)

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

EA5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Further Design ChangesMP06_0172-Mod-3

Decided: approved on 12 Feb 2009 by the department (executive director)

Its page on the Planning Portal

Mod 2 - Design ChangesMP06_0172-Mod-2

Decided: approved on 3 Dec 2008 by the department (executive director)

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - Pedestrian BridgeMP06_0172-Mod-1

Decided: approved on 23 Jan 2008 by the Minister

Its 4 documents

4 documents in 1 folder, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.