On the map
State significant infrastructure

Lord Howe Island Critical Infrastructure Project

New freight, waste and biosecurity facilities, Lord Howe Island

Decided: approved on 17 Aug 2026TransportNeighbourhood scale

Where it is in the process

Approved on 17 Aug 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination17 Aug 2026 (done)
  9. Approved17 Aug 2026

What it proposes

AI summary. Written from this project's page and its Lord Howe Island CIP_Assessment Report_final signed and Lord Howe Island CIP_Notice of Decision_final on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

New freight, waste and biosecurity facilities, Lord Howe Island

The project is new marine and freight handling infrastructure on Lord Howe Island, in the Port Macquarie-Hastings council area. It includes a piled vessel ramp and mooring dolphins, biosecurity facilities, a reconfigured waste management facility, kennels for biosecurity detection dogs and a self-service fuel bowser. The department gives an estimated development cost of $66,131,413, 25 construction jobs and two operational jobs. The project area is a north zone of 21.11 ha and a south zone of 9.9 ha.

The environmental impact statement (EIS) was exhibited from 15 Oct 2025 to 18 Nov 2025 and drew 34 submissions on the portal page: 16 objecting, 4 supporting and 14 commenting. The proponent lodged a submissions report on 4 Mar 2026. The department recommended approval, and the Minister for Planning and Public Spaces approved the project on 17 Aug 2026, subject to conditions. Next, the proponent must meet those conditions before and during construction.

Estimated development cost
$66.1MLord Howe Island CIP_Assessment Report_final signed
Construction jobs
25 jobsLord Howe Island CIP_Assessment Report_final signed
Operational jobs
2 jobsLord Howe Island CIP_Assessment Report_final signed
North zone area
21.11 haLord Howe Island CIP_Assessment Report_final signed
South zone area
9.9 haLord Howe Island CIP_Assessment Report_final signed
Fuel bowser storage capacity
16,000 litresLord Howe Island CIP_Assessment Report_final signed

The department's description

The Project proposes the construction, operation and maintenance of new marine infrastructure, cargo handling facility, biosecurity infrastructure and waste management facility on Lord Howe Island, and associated landscape and vegetation restoration.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

34 submissions: 33 from the public and 1 from organisations

Object16
Support4
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

55 documents in 10 folders, each on the NSW Planning Portal

Notice of Exhibition1
Application2
SEARs1
EIS28
Response to Submissions4
Agency Advice10
Additional Information4
Determination3
Reports1
Notifications1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.