Decided: approved on 30 Nov 2020Health

Where it is in the process

Approved on 30 Nov 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination30 Nov 2020 (done)
  9. Approved30 Nov 2020

What it proposes

The department's description

Construction and operation of a seven level carpark at Liverpool Hospital, including: multi-level and at-grade carparks with 1,097 car parking and 55 motorcycle parking spaces; demolition works; remediation works; road connections; and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 1 from the public and 8 from public authorities

Object0
Support1
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Liverpool Hospital Carpark MOD 2 - GTP and wasteSSD-10388-Mod-2

Decided: approved on 30 Jan 2025 by the department (team leader)

Changes to conditions of consent relating to landscaping, the Green Travel Plan and operational waste management.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Liverpool Hospital Carpark MOD 1 - Design changesSSD-10388-Mod-1

Decided: approved on 9 Dec 2021 by the department (team leader)

New facade incorporating artwork, introduction of a safety screen along the entry and exit ramp, increased rooftop safety parapet, provision of solar panels and reduction of four parking spaces.

Its 11 documents

11 documents in 3 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.