Lingard Private Hospital Expansion
Lingard Private Hospital expansion, Merewether
Where it is in the process
Approved on 10 Dec 2025
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Lingard Private Hospital expansion, Merewether
The project expands the existing Lingard Private Hospital campus in Merewether, in the City of Newcastle. It adds two storeys of hospital wards to the main building and one storey of consulting rooms above the day surgery building. It also builds a two-storey hospital building on adjoining land on Hopkins Street, where five homes now stand. It includes 77 additional car parking spaces. The department gives a capital investment of $116,652,008, with 120 construction jobs and 32 additional operational jobs.
The environmental impact statement (EIS) was exhibited from 5 Apr 2024 to 2 May 2024 and drew 14 submissions: 9 objecting, 1 supporting and 4 commenting. The proponent responded on 25 Nov 2024 with minor amendments. The department recommended approval, and its Director approved the project on 10 Dec 2025 as the Minister's delegate, with conditions. Next, the proponent must meet those conditions before construction.
- Capital investment
- $116.7MAssessment Report
- Construction jobs
- 120 jobsAssessment Report
- Additional operational jobs
- 32 jobsAssessment Report
- Additional car parking spaces
- 77 car spacesAssessment Report
The department's description
Hospital expansion to increase beds, operating rooms, parking and consulting rooms.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
14 submissions: 12 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
102 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs2
EIS50
- Appendix A_SEARs Table
- Appendix B_Architectural Drawings
- Appendix B_Design Report
- Appendix C_Stat Compliance Table
- Appendix D_Community Engagement Table
- Appendix E_Mitigation Measures Table_CURRENT
- Appendix F_Arborist Report
- Appendix G_BCA - Kingsland Precinct
- Appendix G_BCA - Lingard & Hopkins Precincts
- Appendix HH_ACHAR
- Appendix H_BDAR Waiver & Report
- Appendix I - CIV
- Appendix J_Civil and Stormwater Plans
- Appendix K_Clause 4.6 (Height)
- Appendix L_Connection to Country
- Appendix M_Detailed Site Investigation Report
- Appendix M_Phase 1 Preliminary Site Investigation
- Appendix N_DCP Table
- Appendix O_ESD Report
- Appendix O_Embodied Emissions Form (NSW SEPP)
- Appendix O_Net Zero Statement
- Appendix P_Flood Risk Assessment
- Appendix Q_Geotechnical Report
- Appendix R_Hazard Analysis
- Appendix S_European Heritage Report
- Appendix T_Landscape Plans
- Appendix T_Landscape Report
- Appendix U_Acoustic
- Appendix V_Services Concept Report
- Appendix W_Social Impact Assessment
- Appendix X_Kingsland Survey
- Appendix X_Survey Plan
- Appendix Y_State Design Review Panel
- Appendix Z_Traffic Impact Assessment
- Application_20231218023914
- Environmental Impact Statement
- Exhibition Notice
- XAppendix AA_Visual Impact Assessment
- XAppendix BB_Executed VPA
- XAppendix CC_Construction Waste Management Plan
- XAppendix CC_Operational Waste Management Plan
- XAppendix DD_Mines Investigation Report
- XAppendix DD_Mines Remediation Report
- XAppendix EE_Construction Traffic Management Plan
- XAppendix FF_GreenTravel Plan
- XAppendix GG_CPTED Report
- XAppendix II_Access Report
- XAppendix JJ_Hazardous Hopkins
- XAppendix JJ_Hazardous Lingard
- XAppendix KK_Acid Sulphate Management Plan
Response to Submissions23
- Appendix A – Amended Plan Set
- Appendix B – Amended Civils & Stormwater
- Appendix B – Civil & Stormwater Response Letter
- Appendix C – Amended Landscape Plan
- Appendix C – Amended Landscape Report
- Appendix D - RAP
- Appendix D – Detailed Site Investigation
- Appendix E – Amended Flood Risk Assessment
- Appendix E – Flood Risk Response
- Appendix F – Amended s4.6 Variation Request
- Appendix G – Traffic Response Letter
- Appendix H – Amended Heritage Impact Statement
- Appendix I – Amended Visual Impact Assessment
- Appendix J - Amended Hazards Assessment
- Appendix K – Cost Summary Report
- Appendix L – AHIMS
- Appendix M – Grout Implementation Plan
- Appendix N – Peer Review of Mine Subsidence Assessment
- Appendix O – Amended Preliminary Hazard Assessment
- Appendix P – Amended Mitigation Measures
- Appendix Q – Submissions Register
- Request RTS Letter
- Response to Submissions Report
Agency Advice7
Additional Information14
- Amended Architectural Plans
- Amended Flood Emergency Response Plan v2
- Amended Flood Impact and Risk Assessment & FERP - final
- Appendix A - Shadow Diagrams (Amdended)
- Appendix B - Cost Summary (Amended)
- Appendix C - Amended Flood Emergency Response Plan v1
- Appendix D - Northrop Flood Response v2
- Ground Floor Generator Location Plan
- Northrop Flood Response Letter
- RFI Response1
- RFI Response2
- Request for Additional Information1
- Request for Additional Information2
- Request for Additional Information3
What's near it
Where it is
- Suburb
- Merewether
- Council area
- Newcastle
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.