On the map
State significant development

Lindfield Learning Village

Decided: approved on 12 Nov 2020Education

Where it is in the process

Approved on 12 Nov 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination12 Nov 2020 (done)
  9. Approved12 Nov 2020

What it proposes

The department's description

Staged construction and operation of Lindfield Learning Village.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

164 submissions: 139 from the public, 13 from organisations and 12 from public authorities

Object111
Support9
Comment44

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

6 changes to the project after its decision, each assessed as a case of its own, newest first.

Modification 4 Deletion of Conditions A22 and B55SSD-8114-Mod-4

Withdrawn: withdrawn

Section 4.55 (1) - Deletion of conditions A22 and B55 of Phase 1 Partial Consent of SSD 8114.

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Lindfield Learning Village MOD 6 - OOSHSSD-8114-Mod-6

Decided: approved on 12 May 2025 by the department (executive director) · 3 submissions

The proposed modifications seek to relocate the Out of School Hours Care to Levels 0 and 1 of the Western Building and Level 1 of the Main Building and install an intercom and self-closing mechanism to the access gate near the lower carpark.

Its 27 documents

27 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Lindfield Learning Village Mod 5 rooftop plantSSD-8114-Mod-5

Decided: approved on 21 Dec 2021 by the department (team leader)

Modification to rooftop plant services Mod 5

Its 17 documents

17 documents in 4 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application11

See the 11 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Lindfield Learning Village MOD 3 - Phase 1 condSSD-8114-Mod-3

Decided: approved on 18 Mar 2021 by the department (director)

Modifications of conditions that relate to the Phase 1 operation of the development.

Its 5 documents

5 documents in 2 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Lindfield Learning Village MOD 2 - LandscapingSSD-8114-Mod-2

Decided: approved on 12 Mar 2021 by the department (director)

Amendments to approved landscaping plans.

Its 13 documents

13 documents in 4 folders, each on the NSW Planning Portal

Modification Application8

See the 8 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Lindfield Learning Village MOD 1 - Design changesSSD-8114-Mod-1

Decided: approved on 15 Jan 2020 by the department (director)

Temporary increase in students numbers.

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.