On the map
State significant development

Light Horse Interchange Warehouse - Lot 1

Decided: approved on 20 Dec 2023Industry and warehouses

Where it is in the process

Approved on 20 Dec 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination20 Dec 2023 (done)
  9. Approved20 Dec 2023

What it proposes

The department's description

Construction and operation of a warehouse facility on Lot 1 of the Light Horse Interchange Business Hub.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

3 submissions: 2 from organisations and 1 from public authorities

Object2
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Light Horse Lot 1 MOD 1 - Signage ChangesSSD-49584708-Mod-1

Decided: approved on 4 Oct 2024 by the department (team leader)

Modification for the inclusion of a 12m high pylon sign located at the north-eastern corner of Lot 1.

Its 10 documents

10 documents in 4 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.