On the map
State significant development

Liddell Battery and Bayswater Ancillary Works

Decided: approved on 8 Mar 2022Energy: batteries

Where it is in the process

Approved on 8 Mar 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination8 Mar 2022 (done)
  9. Approved8 Mar 2022

What it proposes

The department's description

To construct and operate of a Battery Energy Storage System, decouple Liddell and Bayswater power stations, facilitate the improved safety, reliability, efficiency and environmental performance of Bayswater Power Station

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

17 submissions: 2 from the public, 1 from organisations and 14 from public authorities

Object1
Support0
Comment16

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Liddell Battery and BAW MOD 4 - Administrative modificationSSD-8889679-Mod-4

Under way: at assessment

Administrative modification to update definition in the consent

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 3 Offset staging and minor amendmentsSSD-8889679-Mod-3

Decided: approved on 18 Jun 2025 by the department (team leader)

Changes to how biodiversity credits are staged for the Liddell Battery and Bayswater works, near Muswellbrook, approved by the department on 18 Jun 2025.

The department's description

Amendments to biodiversity credit staging and other minor modifications

Its 6 documents

6 documents in 4 folders, each on the NSW Planning Portal

Early Consultation2
Modification Application1
Determination2
Consolidated Consent1

Its page on the Planning Portal

MOD 2 Transmission Line EasementSSD-8889679-Mod-2

Decided: approved on 11 Apr 2025 by the department (director)

Modification of the approval boundary to include a 330kV transmission line easement

Its 5 documents

5 documents in 4 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 Revised Offset StagingSSD-8889679-Mod-1

Decided: approved on 27 Feb 2024 by the department (director)

Administrative modification to amend the staging for the retirement of biodiversity credits

Its 8 documents

8 documents in 6 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.