Leichhardt Oval Refurbishment
Refurbishing Leichhardt Oval, 68 Mary Street, Lilyfield
Where it is in the process
Approved on 24 Jul 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Refurbishing Leichhardt Oval, 68 Mary Street, Lilyfield
Inner West Council proposed to refurbish Leichhardt Oval at 68 Mary Street, Lilyfield, in the Inner West area. The works upgrade the Western Grandstand and seating bowl and build a new Northern Grandstand. Seated capacity would rise from about 6,381 to about 8,717 seats, while total capacity stays at about 19,000 people. It removes 13 trees and plants 33 new ones. The project provides 137 construction jobs and no extra operational jobs. No capital investment is stated.
The environmental impact statement (EIS) was exhibited from 16 Jan 2026 to 12 Feb 2026. The portal records 23 submissions: 10 objecting, 6 supporting and 7 commenting. The proponent amended the project on 15 May 2026. The department's assessment report recommended approval, and a director of the department, as the Minister's delegate, approved it on 24 Jul 2026, with conditions. Next, the proponent must meet the conditions, including management plans before construction starts.
- Construction jobs
- 137 jobsAssessment Report
- Proposed seated capacity
- 8,717 seatsAssessment Report
- Existing seated capacity
- 6,381 seatsAssessment Report
- Total capacity (unchanged)
- 19,000 peopleAssessment Report
- Trees to be removed
- 13 treesAssessment Report
- New trees to be planted
- 33 treesAssessment Report
The department's description
Refurbishment and upgrade works to Leichhardt Oval including upgrades to the existing Western Grandstand, seating bowl and new northern grandstand.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
23 submissions: 20 from the public, 2 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
74 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs2
SEARs1
EIS38
- Appendix A - SEARs Compliance Table
- Appendix AA - Social Impact Assessment
- Appendix B - Statutory Compliance Table
- Appendix BB - Engagement Report
- Appendix CC - Leichhardt Oval Master Plan
- Appendix D - Design Report
- Appendix DD - Mitigation Measures
- Appendix E - Architectural Drawings
- Appendix F - Survey Plan
- Appendix G - BCA Report
- Appendix H - Accessibility Report
- Appendix I - Pedestrian Wind Environment Assessment
- Appendix J - Visual Impact Analysis
- Appendix K - CPTED Report
- Appendix L - Arboricultural Impact Assessment Report
- Appendix M - Landscape Plans
- Appendix N - ESD Report
- Appendix N - Net Zero Statement
- Appendix O - Green Travel Plan
- Appendix O - Preliminary CTPMP
- Appendix O - Traffic, Transport & Accessibility Assessment
- Appendix P - BDAR waiver letter
- Appendix Q - Noise and Vibration Impact Assessment
- Appendix R - Geotechnical Investigation
- Appendix S - IWMIDP
- Appendix T - Flood Statement
- Appendix U - Preliminary Hazard Analysis
- Appendix V - Construction Environmental Management Plan
- Appendix V - Factual Report on Contamination Testing
- Appendix V - LTEMP
- Appendix V - Letter of Suitability
- Appendix W - ACHAR
- Appendix X - Statement of Heritage Impact
- Appendix Y - CDWMP
- Appendix Y - Operational Waste Management Plan
- Appendix Z - Hazmat
- Application_20251212062954
- EIS
Response to Submissions1
Agency Advice8
Amendments12
- Amended Application form
- Amendment Acceptance Letter
- Amendment and Submissions Report_V05
- Appendix D - Design Report (RTS)
- Appendix DD - Mitigation Measures Table_Leichhardt Oval_RTS
- Appendix E - Architectural Drawings (RTS)
- Appendix L - Arboricultural Impact Assessment Report
- Appendix M - Landscape (RTS)
- Appendix O - Green Travel Plan (RTS)
- Appendix W - ACHAR (RTS) Redacted
- Appendix X - SoHI (RTS)
- Appendix Y - C&D WMP (RTS)
Additional Information6
Notifications1
What's near it
Where it is
- Suburb
- Lilyfield
- Council area
- Inner West
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.