On the map
Part 4 development

Lee Wharf Stg 3 - A3, A4, A5 & A6

Decided: approved on 24 Jan 2007Transport

Where it is in the process

Approved on 24 Jan 2007

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination24 Jan 2007 (done)
  10. Approved24 Jan 2007

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 2 - Delete requirement for s94 contributionDA158-7-2005-Mod-2

Decided: refused on 7 Mar 2008 by the department (director-general)

Its page on the Planning Portal

Mod 1 - 16 residential units to 12 communitsDA158-7-2005-Mod-1

Decided: approved on 11 Jul 2007

Lee Wharf Stg 3 - A3, A4, A5 & A6 (Mod 1)

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.