Kurri Kurri Lateral Pipeline Project

Decided: approved on 23 Dec 2022Energy: other

Where it is in the process

Approved on 23 Dec 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination23 Dec 2022 (done)
  9. Approved23 Dec 2022

What it proposes

The department's description

To develop a ~21 km underground gas pipeline from the existing Sydney to Newcastle pipeline to the Hunter Power Project near Kurri Kurri, a compressor station & a 24 km underground gas storage pipeline & ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

24 submissions: 12 from the public, 9 from organisations and 3 from public authorities

Object19
Support0
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 Stormwater Discharge and Creek Stabilisation WorksSSI-22338205-Mod-1

Decided: approved on 15 Aug 2024 by the department (director)

A new stormwater discharge point and a 0.03 ha work area for the Kurri Kurri Lateral Pipeline, approved by the department on 15 Aug 2024.

The department's description

Changes to operational stormwater management and additional creek stabilisation works

Its 18 documents

Its page on the Planning Portal

MOD 2 Minor Access Track WorksSSI-22338205-Mod-2

Decided: approved on 2 May 2024 by the department (director)

Minor extension of construction access tracks

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.