Decided: approved on 20 Dec 1979Energy: other

Where it is in the process

Approved on 20 Dec 1979

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination20 Dec 1979 (done)
  9. Approved20 Dec 1979

What it proposes

The department's description

An approximately 33 km natural gas pipeline between Killingworth and Kooragang Island.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Killingworth to Kooragang Island Gas Pipeline MOD 3 - Hunter LateralSSI-46360740-Mod-3

Under way: at response to submissions · 24 submissions

Construction and operation of a new high-pressure gas pipeline and associated infrastructure between Millers Forest and Hexham to connect the Killingworth to Kooragang Island Gas Pipeline to the Queensland Hunter Gas Pipeline.

Its 28 documents

28 documents in 5 folders, each on the NSW Planning Portal

Notice of Exhibition2

See the 2 documents on the Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application14

See the 14 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Agency Advice10

See the 10 documents on the Planning Portal

Its page on the Planning Portal

Killingworth to Kooragang Island Gas Pipeline MOD 2 - Correction to credit liabilitySSI-46360740-Mod-2

Decided: approved on 3 Apr 2024 by the department (director)

Modification to fix transcription error in credit liability

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Killingworth to Kooragang Island Gas Pipeline MOD 1 - Lenaghan LateralSSI-46360740-Mod-1

Decided: approved on 9 Aug 2023 by the department (director) · 3 submissions

Construction and operation of a new pipeline connection and associated infrastructure at Lenaghan to allow the transmission of gas between the existing Killingworth to Kooragang Island Gas Pipeline and the Kurri Kurri Lateral Pipeline.

Its 28 documents

28 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Early Consultation2

See the 2 documents on the Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice8

See the 8 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

8 documents in 3 folders, each on the NSW Planning Portal

Determination1

See the document on the Planning Portal

Management Plans and Strategies3

See the 3 documents on the Planning Portal

Other Documents4

See the 4 documents on the Planning Portal

Where it is

The register gives no exact place for it, only “Killingworth to Kooragang Island Gas Pipeline”, so it is shown at the middle of its council area on the map, and this page names no suburb or neighbours.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.