Kelso Crescent Multi-Level Warehouse, Moorebank
A two-storey warehouse and distribution centre, Moorebank
Where it is in the process
Approved on 19 Aug 2026
What it proposes
AI summary. Written from this project's page and its SSD Instrument of Consent and SSD-SSI Assessment Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A two-storey warehouse and distribution centre, Moorebank
The project is a two-storey warehouse and distribution centre at 20 Kelso Crescent, Moorebank, in the Liverpool City Council area, on a vacant industrial site. It has two warehouse buildings with eight tenancies, up to 25.1 m high, and a gross floor area of 33,749 m². It would operate 24 hours a day. The department gives a capital investment of $94,500,000, with up to 160 construction jobs and 240 operational jobs.
The environmental impact statement (EIS) was exhibited from 4 June 2024 to 1 July 2024, and the amended application from 6 November 2025 to 19 November 2025. The case drew 6 submissions: 1 objecting, 1 supporting and 4 commenting. The department's Director approved it on 19 Aug 2026 as the Minister's delegate. Next, the proponent must meet the consent's conditions, including traffic, noise and flood management plans, before construction.
- Capital investment
- $94.5MSSD-SSI Assessment Report
- Construction jobs
- 160 jobsSSD-SSI Assessment Report
- Operational jobs
- 240 jobsSSD-SSI Assessment Report
- Building height
- 25.1 mSSD-SSI Assessment Report
- Gross floor area
- 33,749 m²SSD-SSI Assessment Report
The department's description
Demolition of existing onsite structures and construction and operation of a multi level warehouse and distribution centre, comprised of five tenancies, with mezzanine offices and parking, and associated vehicular access.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
6 submissions: 2 from the public and 4 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
139 documents in 12 folders, each on the NSW Planning Portal
Early Consultation3
Notice of Exhibition2
Request for SEARs2
SEARs2
EIS41
- 20 Kelso Crescent Multi Level Warehouse EIS
- Appendix 1 - SEARs 230424
- Appendix 10 - Landscape Plan - 13.09.2023
- Appendix 10 - Landscape Plan Specification
- Appendix 11 - Aboricultural Impact Assessment
- Appendix 12 - ESD Report - 27.03.2024
- Appendix 14 - Air Quality Assessment
- Appendix 15 - Noise & Vibration Assessment
- Appendix 16 - CNVMP
- Appendix 17 - Geotechnical Investigation
- Appendix 17 - Geotechnical Report
- Appendix 18 - Detailed Site Investigation
- Appendix 19 - Fire Safety Design Review
- Appendix 2 - Estimated Development Cost
- Appendix 20 - Civil Report
- Appendix 21 - Flood Risk Assessment
- Appendix 22 - Phase 1 Environmental Assessment
- Appendix 23 - Hazard Building Materials Register
- Appendix 24 - Hazardous Building Materials Plan
- Appendix 25 - Remedial Action Plan
- Appendix 26 - Waste Management Plan
- Appendix 27 - Full ACHAR
- Appendix 28 - Statement of Heritage Impact
- Appendix 29 - Socio Economic Impact Assessment
- Appendix 3 - Title Documents [Plan]
- Appendix 30 - Service Infrastructure Assessment
- Appendix 31 - Engagement Report
- Appendix 32 - Endeavour Energy
- Appendix 33 - Plan of Consolidation
- Appendix 34 - Schedule 5 - I&ESEPP Assessment
- Appendix 35 - NABERS Energy Agreement
- Appendix 35 - Signed NABERS (Energy and Water)
- Appendix 36 - Embodied Emissions Materials
- Appendix 4 - Architectural drawings
- Appendix 5 - Design Report - September 2023
- Appendix 6 - Detail Survey Plan
- Appendix 7 - Regulatory Compliance & Accessibility
- Appendix 8 - Visual Analysis - 13.09.2023
- Appendix 9 - TIA - 14.09.2023
- Application_20240422215329
- BDAR Waiver Request
Response to Submissions18
- Appendix D1 - RTS Response Matrix
- Appendix D2 - Section 88B Instrument for Lot Amalgamation
- Appendix D3 - Revised Architectural Drawings
- Appendix D4 - Updated Landscape Package
- Appendix D5 - Traffic Assessment Addendum
- Appendix D6 - Flood Assessment Addendum
- Appendix D7 - Flood Emergency Response Plan
- Appendix D8 - Noise Impact Assessment Addendum
- D1_Architectural Drawings_March 2026
- D2_Architectural Response_March 2026
- D3_Updated Landscape Plans_March 2026
- D4_Landscape RTS_March 2026
- D5_Flood Impact Risk Assessment_March 2026
- D6_Civil Report and Plans_March 2026
- Kelso Crescent RTS - SSD-58978472_March 2026
- Request RTS
- Request RTS Letter
- WTJ23-142 - Response to Submissions Report - SSD-58978472
Agency Advice24
- BCS Response to EIS
- CPHR - MultiLevel Warehouse Kelso Cr Moorebank SSD58978472
- CPHR - RTS - Kelso Cres Moorebank SSD-58978472
- CPHR Amendment Report Kelso Cr SSD58978472
- Council Response - April 2026
- Council Response on Amendment Report
- Council response to RTS
- EPA Response to EIS
- EPA Response-Kelso Crescent Multi-Level Warehouse
- FRNSW - Amend Report - Kelso Crescent Multi Level W/H
- FRNSW Response to EIS
- FRNSW response to RTS
- HNSW ACH - Amend - Kelso Cres Warehouse - SSD-58978472
- HNSW Aboriginal Heritage Response to EIS
- HNSW EH SSD-58978472 Amendment_AppId_12432
- Heritage NSW Response to EIS
- SSD1-5-2024-Kelso Crescent-RTS-2
- Sydney Water DA Information Sheet (May 2024)
- Sydney Water Response to EIS
- TfNSW Response SYD24-01042-03
- TfNSW Response to EIS
- TfNSW Response to RTS
- WNSW response - Kelso Cres Warehouse - Amendment rpt
- Water NSW Response to EIS
Amendments17
- Amended Application_20251017080150
- Amendment Acceptance Letter
- Appendix DD10_BDAR Waiver Request
- Appendix DD11_Regulatory Compliance
- Appendix DD12_Air quality Impact Assessment
- Appendix DD13_Social Impact Assessment
- Appendix DD14_Sustainability Mgt Plan statement
- Appendix DD1_Architectural Plans
- Appendix DD2_Architectural Report
- Appendix DD3_Landscape Plans
- Appendix DD4 Civil Report and Plans
- Appendix DD5 Flood Impact Risk Assessment
- Appendix DD6_Visual Impact Assesment
- Appendix DD7_Arboricultural Impact Assessment
- Appendix DD8 Transport Impact Assesment
- Appendix DD9_Noise and Vibration Impact Assessment
- Kelso Crescent Amendment Report 17.10.25
Additional Information15
- 24023 - ATC - Moorebank Ave - LIVERPOOL
- Applicant comments on draft conditions
- Council Comments RTS 2
- D1_Architectural Drawings_March 2026
- D2_Architectural Response_March 2026
- D3_Updated Landscape Plans_March 2026
- D4_Landscape RTS_March 2026
- D5_Flood Impact Risk Assessment_March 2026
- D6_Civil Report and Plans_March 2026
- Kelso Cr RFI
- Kelso Cr RFI 120325
- Kelso Crescent RTS - SSD-58978472_March 2026
- Request for Additional Information201224
- _Council+response+to+RTS_
- _TfNSW+Response+to+RTS_
Determination8
Management Plans and Strategies5
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.