On the map
State significant development

Kamay Battery Energy Storage System

A 150 MW battery at Captain Cook Drive, Kurnell

Under way: at response to submissionsEnergy: batteriesDistrict scale

Where it is in the process

At response to submissions

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (current stage)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 150 MW battery at Captain Cook Drive, Kurnell

The proponent proposes to build, operate and later decommission a battery energy storage system at 171-189 Captain Cook Drive, Kurnell, in the Sutherland Shire. It would have a maximum power output of up to 150 MW with a 2-hour duration, or 300 MWh, plus supporting equipment. The environmental impact statement (EIS), prepared for Ausgrid and dated 21 May 2026, describes a site that already holds an electricity substation. No capital investment or job numbers are stated.

The case is at the response to submissions stage. The EIS was exhibited and drew 125 submissions: 120 objecting, 3 supporting and 2 commenting. The proponent must now respond to them and may amend the project. The department then assesses the project with advice from other agencies and writes an assessment report. The department or the Independent Planning Commission then decides it. No exhibition or response dates are given.

Maximum power output
150 MWPortal page
Storage capacity
300 MWhPortal page
Public submissions
125 submissionsPortal page
Submissions objecting
120 submissionsPortal page

The department's description

Construction, operation and decommissioning of a Battery Energy Storage System (BESS) with an up to 150 Megawatt (MW) maximum power output capacity with 2-hour duration (300MWh) and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

125 submissions: 114 from the public, 10 from organisations and 1 from public authorities

Object120
Support3
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

51 documents in 5 folders, each on the NSW Planning Portal

Request for SEARs1
SEARs1
EIS20
Response to Submissions1
Agency Advice28

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.