Julius Avenue Data Centre

A 120 MW data centre at Julius Avenue, North Ryde

Under way: at recommendationData centresRegional scale

Where it is in the process

At recommendation

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (current stage)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its SSD-80018208 - DPHI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 120 MW data centre at Julius Avenue, North Ryde

The proponent proposes a 24-hour data centre at 6-8 Julius Avenue, North Ryde, in the City of Ryde. As amended, it would use up to 120 MW, with eight data halls and a building up to 40 m high. It would have 48 diesel back-up generators and 96 air-cooled chillers, and would remove 334 trees. The estimated development cost is about $1.267 billion. It would create up to 380 construction jobs and 50 operational jobs.

The original proposal was exhibited from 31 Jul 2025 to 27 Aug 2025, and the amended proposal from 5 Mar 2026 to 18 Mar 2026. The portal records 187 submissions: 175 objecting, 2 supporting and 10 commenting. The department's assessment report of October 2026 found the project approvable, subject to conditions. The Independent Planning Commission is to decide. If it approves, the proponent must meet the conditions of consent.

Capital investment
$1.27bnSSD-80018208 - DPHI Assessment Report
Power consumption
120 MWSSD-80018208 - DPHI Assessment Report
Construction jobs
380 jobsSSD-80018208 - DPHI Assessment Report
Operational jobs
50 jobsSSD-80018208 - DPHI Assessment Report
Maximum building height
40 mSSD-80018208 - DPHI Assessment Report
Back-up diesel generators
48 generatorsSSD-80018208 - DPHI Assessment Report
Trees to be removed
334 treesSSD-80018208 - DPHI Assessment Report
Site area
28,630 m²SSD-80018208 - DPHI Assessment Report

The department's description

Construction and 24/7 operation of a data centre with a power consumption of up to 170 megawatts, comprising a six-storey building, office space, diesel storage, back-up generators, car parking and a subtransmission switching station, and a new road.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

187 submissions: 175 from the public, 10 from organisations and 2 from public authorities

Object175
Support2
Comment10

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

146 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition2
Request for SEARs2
SEARs2
EIS42
Response to Submissions14
Agency Advice35
Amendments42
Additional Information4
Recommendation3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.