On the map
State significant development

Jemalong Solar Farm

Decided: approved on 18 May 2018Other

Where it is in the process

Approved on 18 May 2018

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination18 May 2018 (done)
  8. Approved18 May 2018

What it proposes

The department's description

Development of a 50 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 2 from the public and 7 from organisations

Object2
Support0
Comment7

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Jemalong Solar Farm Modification 4SSD-8803-Mod-4

Decided: approved on 4 Dec 2025 by the department (director)

Minor extension of the development footprint to enable the construction of minor drainage works necessary to reduce waterlogging and improve the success of the landscape screening required by Schedule 3- Condition 10.

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

MOD 3 - Transmission LineSSD-8803-Mod-3

Decided: approved on 13 Nov 2019 by the department (director)

Convert sections of high voltage transmission line from underground to overhead and an increase to the inverter height

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 2 - Revised Development FootprintSSD-8803-Mod-2

Decided: approved on 3 Sep 2019 by the department (director)

A revised development footprint as a result of detailed design refinements

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Jemalong Solar MOD 1 - Subdivision ChangesSSD-8803-MOD-1

Decided: approved on 30 Jul 2018 by the department (director)

Administrative modification to amend the subdivision plan for the project site.

Its 6 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Jemalong
Council area
Forbes

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Other State projects near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.