On the map
State significant development

Ivanhoe Estate redevelopment - Stage 1

Decided: approved on 30 Apr 2020Mixed use

Where it is in the process

Approved on 30 Apr 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination30 Apr 2020 (done)
  9. Approved30 Apr 2020

What it proposes

The department's description

Ivanhoe Estate State 1 comprising new internal road network and construction of Buildings A1 and C1.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

31 submissions: 23 from the public, 2 from organisations and 6 from public authorities

Object23
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

7 changes to the project after its decision, each assessed as a case of its own, newest first.

Ivanhoe Estate Stage 1 MOD 7 - Stormwater DesignSSD-8903-Mod-7

Decided: approved on 11 May 2023 by the department (team leader)

Amendments to stormwater design and removal of 14 additional trees

Its 16 documents

16 documents in 4 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Ivanhoe Estate Stage 1 MOD 6 - Increased HeightSSD-8903-Mod-6

Decided: approved on 23 Dec 2022 by the department (team leader)

Increase in height of of Building A1 by 565 mm.

Its 9 documents

9 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Ivanhoe Estate Stage 1 MOD 5 - Amendments to C1SSD-8903-Mod-5

Decided: approved on 19 Dec 2022 by the department (team leader)

- Amendments to the configuration of apartments and Basement 1, material on the terrace façade, and exhaust and plant locations - Relocation of communal lift - Provision of access from Building C1 to Building C2 - Fit out of community room

Its 14 documents

14 documents in 4 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination5

See the 5 documents on the Planning Portal

Its page on the Planning Portal

Ivanhoe Estate Stage 1 MOD 4 - Tree removalSSD-8903-Mod-4

Decided: approved on 5 Aug 2022 by the department (director)

Removal of seven (7) trees that were approved for retention

Its 15 documents

15 documents in 5 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Ivanhoe Estate Stage 1 MOD 3 - Tree RemovalSSD-8903-Mod-3

Decided: approved on 21 Dec 2021 by the department (team leader)

Removal of three (3) trees that were approved for retention, and retention of two (2) trees that were approved for removal.

Its 10 documents

10 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Ivanhoe Estate Stage 1 MOD 2 - Building C1 ChangesSSD-8903-Mod-2

Decided: approved on 7 May 2021 by the department (director)

Conversion of 105 market dwellings to 130 affordable housing dwellings within Building C1 resulting in a net increase of 25 dwellings (471 to 496) plus 24 additional car parking spaces. Associated internal and external alterations.

Its 18 documents

18 documents in 2 folders, each on the NSW Planning Portal

Modification Application12

See the 12 documents on the Planning Portal

Determination6

See the 6 documents on the Planning Portal

Its page on the Planning Portal

Ivanhoe Estate Stage 1 MOD 1 - ConditionsSSD-8903-Mod-1

Decided: approved on 10 Nov 2020 by the department (director)

MOD 1 - Amendments to conditions of consent

Its 12 documents

12 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.