Integra Underground Mine

Decided: approved on 26 Nov 2010Mining

Where it is in the process

Approved on 26 Nov 2010

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination26 Nov 2010 (done)
  8. Approved26 Nov 2010

What it proposes

The department's description

Integra Underground Mine

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

11 changes to the project after its decision, each assessed as a case of its own, newest first.

Integra Underground Mod 11 - Administrative ModificationMP08_0101-Mod-11

Under way: at assessment

Separation of the Integra Underground Mine Project Approval (PA 08_0101) into two discrete areas of responsibility for the respective activities to relfect ownership of the site (Integra West Area and Integra East Area)

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Its page on the Planning Portal

Modification 10 - Integra / Mt Owen water transfersMP08_0101-Mod-10

Decided: approved on 9 Sep 2025 by the department (director)

The proposed modification involves water transfers from Mt Owen to Integra, pumping this water into underground workings and construction of pipelines and services to facilitate these activities

Its 14 documents

14 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Modification 9 - RMP ConditionsMP08_0101-Mod-9

Decided: approved on 17 May 2023 by the department (director)

Administrative modification to update Rehabilitation Management Plan conditions to reflect recent reforms of the Mining Regulation 2016.

Its 5 documents

5 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Integra Undeground MOD8 - Additional & Extended LongwallsMP08_0101-Mod-8

Decided: approved on 16 Apr 2018 by the Independent Planning Commission

/

Its 40 documents

Its page on the Planning Portal

Integra Underground MOD7 - Water Pipeline ConstructionMP08_0101-Mod-7

Decided: approved on 15 Sep 2017 by the Independent Planning Commission

/

Its 21 documents

Its page on the Planning Portal

Integra Underground MOD6 - Revised Project LayoutMP08_0101-Mod-6

Decided: approved on 21 Dec 2016 by the Independent Planning Commission

/

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

EA1

See the document on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Integra Underground MOD5 - Separation of consentsMP08_0101-Mod-5

Decided: approved on 23 Aug 2016 by the Independent Planning Commission

/

Its 13 documents

Its page on the Planning Portal

Integra Underground MOD4 - Biodiersity Offset AreaMP08_0101-Mod-4

Decided: approved on 24 Feb 2016 by the Independent Planning Commission

/

Its page on the Planning Portal

Integra Underground (Mod 2)MP08_0101-Mod-2

Decided: approved on 1 Feb 2013 by the department (deputy secretary)

Its page on the Planning Portal

Integra Underground (Mod 3)MP08_0101-Mod-3

Decided: approved on 5 Oct 2012 by the department (executive director)

Its page on the Planning Portal

Integra Underground (Mod 1)MP08_0101-Mod-1

Decided: approved on 18 Mar 2012 by the department (executive director)

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.