State significant infrastructure

Inland Rail - Narromine to Narrabri

Decided: approved on 21 Feb 2023Transport

Where it is in the process

Approved on 21 Feb 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination21 Feb 2023 (done)
  9. Approved21 Feb 2023

What it proposes

The department's description

This section of the Inland Rail project consists of approximately 300 km of new single track rail line, through private and public property in a “greenfield” environment between Narromine and Narrabri.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

176 submissions: 132 from the public, 24 from organisations and 20 from public authorities

Object114
Support13
Comment49

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Narromine to Narrabri MOD 2 - Credit RetirementSSI-9487-Mod-2

Decided: approved on 1 Oct 2025 by the department (director)

Modification to MCoA E24, to align with MCoA E26 of the Approval for Inland Rail Illabo to Stockinbingal Project (SSI-9406), which allows for the review and reduction the ecosystem and species credit requirements with Planning Secretary approval.

Its 11 documents

11 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Determination5

See the 5 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Narromine to Narrabri MOD 1 - Admin ChangesSSI-9487-Mod-1

Decided: approved on 23 Apr 2024 by the department (director)

Changes requested to conditions including:1. MCoA E56 Erosion Threshold Velocities (ETV) Report2. MCoA E111 Arrow Travelling Stock Reserve (TSR) Alternative Arrangements3. Other minor amendments to conditions

Its 5 documents

5 documents in 2 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.