Inland Rail - Narrabri to North Star Phase 2
Upgrading 15 km of Inland Rail track from Moree to Camurra North
Where it is in the process
Approved on 4 Dec 2025
What it proposes
AI summary. Written from this project's page and its N2NSP2 Instrument of Approval 041225 and Planning Secretary’s Assessment Report 041225 on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Upgrading 15 km of Inland Rail track from Moree to Camurra North
The project upgrades about 15 km of rail track between Moree and Camurra North in the Moree Plains Shire, as part of the Inland Rail freight line. It includes 13.7 km of existing track upgraded, 2.4 km of track and formation to bypass the Camurra hairpin and 1.3 km of new rail spur for the Weemelah line. It also includes about 1,800 new drainage culverts and the rebuilding of eight underbridges. About 150 construction jobs and 50 operational jobs are expected. No capital investment is stated.
The environmental impact statement was exhibited from 21 Sep 2022 to 9 Nov 2022 and drew 20 submissions: 2 objecting, 6 supporting and 12 commenting. The proponent responded on 1 Nov 2024 and the department asked for more information in 2025. The department recommended approval and the Minister approved the project on 4 Dec 2025, with conditions. Next, the proponent must meet those conditions, including plans for flooding, noise and biodiversity, before work starts.
- Track upgraded
- 13.7 kmPlanning Secretary’s Assessment Report 041225
- Camurra hairpin bypass
- 2.4 kmPlanning Secretary’s Assessment Report 041225
- New rail spur for the Weemelah line
- 1.3 kmPlanning Secretary’s Assessment Report 041225
- New drainage culverts
- 1,800 culvertsPlanning Secretary’s Assessment Report 041225
- Construction jobs
- 150 jobsPlanning Secretary’s Assessment Report 041225
- Operational jobs
- 50 jobsPlanning Secretary’s Assessment Report 041225
- Native vegetation to be cleared
- 98.21 haPlanning Secretary’s Assessment Report 041225
- Public submissions
- 20 submissionsPortal page
The department's description
Upgrade of approximately 15 km of the existing rail line track and track
formation within the Narrabri to North Star corridor running from Moree north to beyond the Camurra Bypass, including the Mehi-Gwydir river crossings.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
20 submissions: 16 from the public, 3 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
138 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition2
Application1
EIS61
- App A SEARs
- App B Statutory requirements
- App C Environmental risk assessment
- App D Community consultation
- App E Preliminary land requirements
- App F CEMP outline
- App G Rapid Assessment Framework
- Chapter 10 Biodiversity
- Chapter 11 Traffic and transport
- Chapter 12 Hydrology and flooding
- Chapter 13 Surface water quality
- Chapter 14 Groundwater
- Chapter 15 Cultural heritage
- Chapter 16 Noise and vibration
- Chapter 17 Social impact assessment
- Chapter 18 Economics
- Chapter 19 Visual impact assessment
- Chapter 1–8 Introduction
- Chapter 20 Soils and contamination
- Chapter 21 Waste
- Chapter 22 Climate change
- Chapter 23 Sustainability
- Chapter 24 Air quality and greenhouse gas
- Chapter 25 Health & safety
- Chapter 26 Cumulative impacts
- Chapter 27 Approach to environmental management
- Chapter 28 Conclusion & justification of proposal
- Chapter 29 References
- Chapter 9 Land use and property
- Glossary and abbreviations
- Tech Paper 1 Biodiversity development assessment
- Tech Paper 10 Construction noise & vibration
- Tech Paper 11 Operational noise & vibration
- Tech Paper 2 Post-wet aquatic ecology
- Tech Paper 3 Traffic impact assessment
- Tech Paper 4 Hydrology & Flooding
- Tech Paper 4 Hydrology & Flooding App A1
- Tech Paper 4 Hydrology & Flooding App A2
- Tech Paper 4 Hydrology & Flooding App A3
- Tech Paper 4 Hydrology & Flooding App A4
- Tech Paper 4 Hydrology & Flooding App B1
- Tech Paper 4 Hydrology & Flooding App B2 (1)
- Tech Paper 4 Hydrology & Flooding App B2 (2)
- Tech Paper 4 Hydrology & Flooding App B3
- Tech Paper 4 Hydrology & Flooding App B4
- Tech Paper 4 Hydrology & Flooding App C1
- Tech Paper 4 Hydrology & Flooding App C2
- Tech Paper 4 Hydrology & Flooding App C3
- Tech Paper 4 Hydrology & Flooding App C4
- Tech Paper 4 Hydrology & Flooding App D
- Tech Paper 4 Hydrology & Flooding App E
- Tech Paper 4 Hydrology & Flooding App F
- Tech Paper 4 Hydrology & Flooding App G
- Tech Paper 4 Hydrology & Flooding App H
- Tech Paper 4 Hydrology & Flooding App I
- Tech Paper 5A Surface water impact
- Tech Paper 5B Groundwater impact
- Tech Paper 6 Aboriginal cultural heritage
- Tech Paper 7 Statement of heritage impact
- Tech Paper 8 Social impact assessment
- Tech Paper 9 Economic impact assessment
Response to Submissions23
- N2NS P2 - Letter request for resubmission of PIR & RtS
- N2NS P2 RtS - SoHI
- N2NS P2 RtS App A - Submission Register
- N2NS P2 RtS App B - Mitigation Measures
- N2NS P2 RtS App C - TP 1 BDAR
- N2NS P2 RtS App D - TP 4 Hydrology part 1
- N2NS P2 RtS App D - TP 4 Hydrology part 2
- N2NS P2 RtS App D - TP 4 Hydrology part 3
- N2NS P2 RtS App D - TP 4 Hydrology part 4
- N2NS P2 RtS App D - TP 4 Hydrology part 5
- N2NS P2 RtS App D - TP 4 Hydrology part 6
- N2NS P2 RtS App E - TP 6 Heritage
- N2NS P2 RtS App F - TP 11 Operation Noise and Vib
- N2NS P2 RtS App G - Design Refinements
- N2NS P2 RtS App H - Traffic and Transport
- N2NS P2 RtS App I - Emergency Access Design
- N2NS P2 RtS App J - Land Use and Property
- N2NS P2 RtS App K - updated Construction Footprint
- N2NS P2 RtS App L - supplementary Visual Impact
- N2NS P2 RtS App M - updated Proposal Description
- N2NS P2 RtS App N - EIS Typographic Errors
- N2NS P2 Submissions Report re-lodgement
- Request RTS Letter_17112022_111946
Agency Advice23
- BCS (Biodiversity) - EIS advice SSI-10054
- BCS (Hydrology) - EIS advice SSI-10054
- CPHR (Biodiversity) - RTS/PIR advice SSI-10054
- CPHR (Hydrology) - RTS/PIR advice SSI-10054
- CPHR - Final Credit Obligations - BDAR v8.4
- Crown Lands - EIS advice SSI-10054
- Crown Lands - RTS/PIR advice SSI-10054
- DPE Water - EIS advice SSI-10054
- DPI Fisheries - EIS advice SSI-10054
- DPI Fisheries - RTS/PIR advice SSI-10054
- EPA - EIS advice SSI-10054
- EPA - RTS/PIR advice SSI-10054
- Heritage NSW (ACH) - EIS advice SSI-10054
- Heritage NSW (ACH) - RTS/PIR advice SSI-10054
- Heritage NSW - EIS advice SSI-10054
- Heritage NSW - RTS/PIR advice SSI-10054
- MPSC - RTS/PIR advice SSI-10054
- NSW DCCEEW Water - RTS/PIR advice SSI-10054
- NW Local Land Services - EIS advice SSI-10054
- NWLLS - Updated EIS advice - 30 Mar 23
- TFNSW - RTS/PIR advice SSI-10054
- TfNSW - Updated EIS advice - 16 Mar 23
- Transport for NSW - EIS advice SSI-10054
Amendments6
Additional Information12
- Major RFI Response - Addendum Level Crossing Options - June 2025
- Major RFI Response - BDAR Appendices v8.4 - 9 July 2025
- Major RFI Response - BDAR v8.4 - 9 July 2025
- Major RFI Response - Hydrology RFI Response-230925
- N2NS P2 Major RFI - request Hydrology - 05 Mar 2025
- N2NS P2 Major RFI - request LX563 and revised BDAR - 04.04.25
- N2NS P2 Major RFI - request for updated BDAR - 13.11.24
- N2NS P2 RFI Response - BDAR detailed response - 04.03.25
- N2NS P2 RFI Response - BDAR v8 Appendices
- N2NS P2 RFI Response - BDAR v8 Main Report
- N2NS P2 RFI Response - updated mitigation measures - 04.03.25
- N2NS Phase 2 Major RFI - PIR request 02.03.23
Determination7
Management Plans and Strategies2
What's near it
Where it is
- Suburb
- Moree
- Council area
- Moree Plains
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.