On the map
State significant infrastructure

Inland Rail - Narrabri to North Star Phase 2

Upgrading 15 km of Inland Rail track from Moree to Camurra North

Decided: approved on 4 Dec 2025TransportRegional scale

Where it is in the process

Approved on 4 Dec 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination4 Dec 2025 (done)
  9. Approved4 Dec 2025

What it proposes

AI summary. Written from this project's page and its N2NSP2 Instrument of Approval 041225 and Planning Secretary’s Assessment Report 041225 on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Upgrading 15 km of Inland Rail track from Moree to Camurra North

The project upgrades about 15 km of rail track between Moree and Camurra North in the Moree Plains Shire, as part of the Inland Rail freight line. It includes 13.7 km of existing track upgraded, 2.4 km of track and formation to bypass the Camurra hairpin and 1.3 km of new rail spur for the Weemelah line. It also includes about 1,800 new drainage culverts and the rebuilding of eight underbridges. About 150 construction jobs and 50 operational jobs are expected. No capital investment is stated.

The environmental impact statement was exhibited from 21 Sep 2022 to 9 Nov 2022 and drew 20 submissions: 2 objecting, 6 supporting and 12 commenting. The proponent responded on 1 Nov 2024 and the department asked for more information in 2025. The department recommended approval and the Minister approved the project on 4 Dec 2025, with conditions. Next, the proponent must meet those conditions, including plans for flooding, noise and biodiversity, before work starts.

Track upgraded
13.7 kmPlanning Secretary’s Assessment Report 041225
Camurra hairpin bypass
2.4 kmPlanning Secretary’s Assessment Report 041225
New rail spur for the Weemelah line
1.3 kmPlanning Secretary’s Assessment Report 041225
New drainage culverts
1,800 culvertsPlanning Secretary’s Assessment Report 041225
Construction jobs
150 jobsPlanning Secretary’s Assessment Report 041225
Operational jobs
50 jobsPlanning Secretary’s Assessment Report 041225
Native vegetation to be cleared
98.21 haPlanning Secretary’s Assessment Report 041225
Public submissions
20 submissionsPortal page

The department's description

Upgrade of approximately 15 km of the existing rail line track and track

formation within the Narrabri to North Star corridor running from Moree north to beyond the Camurra Bypass, including the Mehi-Gwydir river crossings.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

20 submissions: 16 from the public, 3 from organisations and 1 from public authorities

Object2
Support6
Comment12

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

138 documents in 10 folders, each on the NSW Planning Portal

Notice of Exhibition2
Application1
SEARs1
EIS61
Response to Submissions23
Agency Advice23
Amendments6
Additional Information12
Determination7
Management Plans and Strategies2

What's near it

Where it is

Suburb
Moree
Council area
Moree Plains

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.