On the map
Part 4 development

Huntsman Ethylene Plant,Port Bontany

Decided: approvedIndustry and warehouses

Where it is in the process

Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The department's description

Huntsman Ethylene Plant,Port Bontany

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Emissions ScrubberDA1789/88-Mod-1

Decided: approved on 21 Dec 2012 by the department (executive director)

Huntsman Ethylene Plant,Port Bontany(Mod 1)

Its page on the Planning Portal

Where it is

The register gives no exact place for it, only “16-20 Beauchamp Road, ,Matraville,New South Wales,2036,Australia”, so it is shown at the middle of its council area on the map, and this page names no suburb or neighbours.

Council area
Bayside

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.