Hunters Hill Remediation

Decided: approved with conditions on 12 Apr 2021Waste

Where it is in the process

Approved With Conditions on 12 Apr 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination12 Apr 2021 (done)
  8. Approved With Conditions12 Apr 2021

What it proposes

The department's description

Excavation and remediation of contaminated soils and off site disposal

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Hunters Hill Remediation MOD 3 - Updated TransportMP08_0008-Mod-3

Decided: approved on 26 Jul 2023 by the department (director)

Revised transport route and final disposal location for the remaining contaminated material.

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Hunters Hills Remediation MOD 2 - Interim Storage ChangesMP08_0008-Mod-2

Decided: approved on 6 May 2022 by the department (director)

• changes to the interim storage location for contaminated material • changes to the port location for the export of contaminated material

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Hunters Hill Remediation MOD 1 - Interim StorageMP08_0008-Mod-1

Decided: approved on 24 Dec 2021 by the department (director)

• changes to the interim storage location for contaminated material; and • changes to the port location for the export of contaminated material.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

15 documents in 3 folders, each on the NSW Planning Portal

Management Plans and Strategies8

See the 8 documents on the Planning Portal

Notifications1

See the document on the Planning Portal

Other Documents6

See the 6 documents on the Planning Portal