A 108 MW vanadium flow battery near Muswellbrook

Under way: at prepare eisEnergy: batteriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report V 3 on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 108 MW vanadium flow battery near Muswellbrook

The proponent proposes a vanadium flow battery with a storage capacity of at least 108 MW and 864 MWh, with up to 200 MW of inverter capacity. It would be on about 44 ha of former Muswellbrook Coal Mine land in the Muswellbrook Shire Council area, within the Hunter-Central Coast Renewable Energy Zone. It would connect to the Sandy Creek substation by one of two transmission options. No capital investment or job numbers are stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). The scoping report is dated 30 Jun 2026, and the Secretary's environmental assessment requirements (SEARs) have been issued. No submissions have been made yet. Next, the proponent lodges the EIS, which is then exhibited so the public can make submissions. Some of the land is not zoned to allow the battery, and the proponent intends to seek a rezoning.

Battery power capacity
108 MWScoping Report V 3
Battery storage capacity
864 MWhScoping Report V 3
Inverter capacity
200 MWScoping Report V 3
Project area
44 haScoping Report V 3

The department's description

Construction, operation and decommissioning of a flow battery with a capacity of 108MW / 864MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.