On the map
Part 4 development

Hunter Valley Mine

Decided: approvedMining

Where it is in the process

Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Hunter Valley MineDA114-12-98-Mod-1

Decided: approved by the Minister

Its page on the Planning Portal

Mod 2 - Introduce and Operate a DraglineDA114-12-98-Mod-2

Decided: approved on 11 Mar 2002 by the Minister

Its page on the Planning Portal

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.