  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination28 Apr 2009 (done)
  10. Approved28 Apr 2009

What it proposes

The portal gives no description.

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Offset TimingMP07_0128-Mod-1

Decided: approved on 2 Jul 2010 by Dir(MIA)

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Clare
Council area
Cessnock

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.