On the map
State significant development

Hume North Battery Energy Storage System

A 75 MW battery on Trout Farm Road, Lake Hume Village

Decided: approved on 31 Mar 2026Energy: batteriesNeighbourhood scale

Where it is in the process

Approved on 31 Mar 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination31 Mar 2026 (done)
  9. Approved31 Mar 2026

What it proposes

AI summary. Written from this project's page and its Development consent for Hume North BESS and Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 75 MW battery on Trout Farm Road, Lake Hume Village

The project is a battery energy storage system of up to 75 MW and 150 MWh, with a substation and connection to the existing 132 kV transmission line, at 32 Trout Farm Road, Lake Hume Village, about 10 km east of Albury in the Albury City area. The development footprint is 1.9 ha. The department gives an estimated cost of $120 million, up to 50 construction jobs and up to 2 operational jobs.

The environmental impact statement was exhibited from 15 Nov 2024 to 13 Dec 2024 and the portal records 78 submissions: 74 objecting, 1 supporting and 3 commenting. The proponent amended the project in October 2025. The department's assessment report of November 2025 found it approvable subject to conditions. The Independent Planning Commission approved it on 31 Mar 2026. Next, the proponent must meet the conditions, including a voluntary planning agreement with the council, before construction.

Estimated development cost
$120MAssessment Report
Battery power capacity
75 MWAssessment Report
Battery storage capacity
150 MWhAssessment Report
Construction jobs
50 jobsAssessment Report
Operational jobs
2 jobsAssessment Report
Development footprint
1.9 haAssessment Report
Project area
4 haAssessment Report

The department's description

74MW/148MWh battery and associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

78 submissions: 66 from the public and 12 from organisations

Object74
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

83 documents in 10 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS19
Response to Submissions2
Agency Advice36
Amendments10
Additional Information7
Recommendation3
Determination3