Homebush Battery Energy Storage System
A 200 MW battery at 10 Homebush Bay Drive, Homebush
Where it is in the process
Approved on 7 Aug 2026
What it proposes
AI summary. Written from this project's page and its IPC - Instrument of Determination and Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 200 MW battery at 10 Homebush Bay Drive, Homebush
Ausgrid proposed a battery energy storage system with a capacity of 200 MW and 431 MWh at 10 Homebush Bay Drive, Homebush, in the Strathfield Council area. It would sit beside the existing Mason Park substation, on a site of 6.2 ha with a development footprint of 2.95 ha. Construction would take about 22 months. The department gives a capital investment of $215 million, up to 100 construction jobs and 1 operational job.
The environmental impact statement (EIS) was exhibited from 19 Jun 2025 to 21 Jul 2025 and drew 63 submissions: 59 objecting, 1 supporting and 3 commenting. The proponent responded and made minor layout changes. The department's assessment report of July 2026 found it approvable subject to conditions. The Independent Planning Commission approved it on 7 Aug 2026. Next, the proponent must meet the conditions, including a voluntary planning agreement with the council, before construction.
- Capital investment
- $215MAssessment Report
- Battery power capacity
- 200 MWAssessment Report
- Battery storage capacity
- 431 MWhAssessment Report
- Construction jobs
- 100 jobsAssessment Report
- Operational jobs
- 1 jobsAssessment Report
- Site area
- 6.2 haAssessment Report
- Development footprint
- 2.95 haAssessment Report
- Construction period
- 22 monthsAssessment Report
The department's description
Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 200MW/431MWh and ancillary infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
63 submissions: 51 from the public, 11 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
MOD 1 - Change in BESS TechnologySSD-77443244-Mod-1
Modification to the battery technology to a 150 MW / 600 MWh BESS.
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
80 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs2
SEARs1
EIS13
- Appendix E Biodiversity Development Assessment Report
- Appendix F1 ACHA
- Appendix G Preliminary and Detailed Site Investigation
- Appendix H Visual Impact Assessment
- Appendix I Noise and Vibration Impact Assessment
- Appendix J Traffic Impact Assessment
- Appendix K Water Impact Assessment
- Appendix L Preliminary Hazard Analysis
- Appendix M Social and Economic Impact Assessment
- Appendix N - Embodied Emissions Technical Note
- Appendix O - EDC Report
- Application Form
- Homebush BESS EIS
Response to Submissions9
- Appendix C2 Response to Heritage NSW Letter
- Appendix D Noise & Vibration memo
- Appendix E Traffic Impact Assessment memo
- Appendix F1 Water Impact Assessment memo and CPHR response
- Appendix F2 Water Impact Assessment memo - Council response
- Appendix G Visual Impact Assessment memo
- Appendix H Preliminary Hazard Analysis memo
- Request RTS Letter
- Submissions Report
Agency Advice32
- Advice on EIS - Ausgrid
- Advice on EIS - CPHR
- Advice on EIS - Crown Lands
- Advice on EIS - DCCEEW Water Group
- Advice on EIS - DPIRD NSW Resources
- Advice on EIS - FRNSW
- Advice on EIS - HNSW ACH
- Advice on EIS - RFS
- Advice on EIS - SOPA
- Advice on EIS - Strathfield Council
- Advice on EIS - Sydney Water
- Advice on EIS - TfNSW
- Advice on RTS - Ausgrid
- Advice on RTS - CPHR
- Advice on RTS - Crown Lands
- Advice on RTS - DPIRD NSW Resources
- Advice on RTS - FRNSW
- Advice on RTS - HNSW (ACH)
- Advice on RTS - NSW DCCEEW Water Group
- Advice on RTS - RFS
- Advice on RTS - SOPA
- Advice on RTS - Strathfield Council
- Advice on RTS - Sydney Water
- Advice on RTS - TfNSW
- Advice on SEARs - BCS
- Advice on SEARs - Crown Lands
- Advice on SEARs - DPIRD NSW Resources (MEG)
- Advice on SEARs - Fire + Rescue NSW
- Advice on SEARs - Heritage NSW (ACH)
- Advice on SEARs - NSW DCCEEW Water
- Advice on SEARs - TfNSW
- Advice on SEARs -Strathfield Council
Additional Information7
- Amended Request for Additional Information (12 November 2025)
- Amended Request for Additional Information (30 March 2026)
- Draft Landscaping Plan (4 May 2026)
- Request for Additional Information (28 October 2025)
- Response to RFI (4 May 2026)
- Updated Mitigation Measures (4 May 2026)
- Updated Project Description (4 May 2026)
Management Plans and Strategies10
- Biodiversity Management Plan
- Biodiversity Management Plan Letter
- Chance Finds Protocol
- Chance Finds Protocol Approval
- Construction Environmental Management Plan
- Construction Environmental Management Plan Letter
- Environmental Management Strategy
- Environmental Management Strategy Approval
- Traffic Management Plan
- Traffic Management Plan Approval
What's near it
Where it is
- Suburb
- Homebush
- Council area
- Strathfield
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.