On the map
State significant development

Holcim Salt Ash Sand Operations

Holcim sand extraction of up to 550,000 tonnes a year, Salt Ash

Under way: at assessmentQuarriesDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Holcim Salt Ash Sand Operations EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Holcim sand extraction of up to 550,000 tonnes a year, Salt Ash

Holcim proposes to extract and process up to 550,000 tonnes a year of sand at its existing quarry at 8 Oakvale Drive, Salt Ash, in the Port Stephens area, using dry extraction and dredging. It would also import up to 200,000 tonnes a year of sand from other local operations, so up to 750,000 tonnes a year would leave the site. The project would run for up to 30 years on a disturbance footprint of about 35.4 ha. No capital investment or job numbers are stated.

The environmental impact statement (EIS) is dated 2 Dec 2022. It was exhibited and drew 26 submissions: 22 objecting, 3 supporting and 1 commenting. The proponent has responded to submissions and lodged an amendment report. The case is now at the stage where the department has asked for more information. Next, the proponent replies, and the department then continues its assessment and decides.

Sand extracted and processed
550,000 tonnes a yearHolcim Salt Ash Sand Operations EIS
Sand imported
200,000 tonnes a yearHolcim Salt Ash Sand Operations EIS
Total sand processed and dispatched
750,000 tonnes a yearHolcim Salt Ash Sand Operations EIS
Project duration
30 yearsHolcim Salt Ash Sand Operations EIS
Disturbance footprint
35.4 haHolcim Salt Ash Sand Operations EIS
Submissions objecting
22 submissionsPortal page

The department's description

Holcim propose to extract and process up to 550,000 tonnes per annum (tpa) of sand at its Salt Ash site using dry extraction and dredging techniques and to import up to 200,000 tpa of sand from their Tanilba Bay, Anna Bay and other local operations.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

26 submissions: 21 from the public, 4 from organisations and 1 from public authorities

Object22
Support3
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

79 documents in 7 folders, each on the NSW Planning Portal

Request for SEARs1
SEARs2
EIS17
Response to Submissions23
Agency Advice28
Amendments4
Additional Information4

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.