On the map
State significant development

Hills of Gold Wind Farm.

Decided: approved on 9 Sep 2024Energy: wind

Where it is in the process

Approved on 9 Sep 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination9 Sep 2024 (done)
  9. Approved9 Sep 2024

What it proposes

The department's description

A wind farm and associated infrastructure located 50 km south-east of Tamworth and 8 km south of Nundle, comprising up to 70 wind turbines, battery storage and grid connection. IPC link: https://www.ipcn.nsw.gov.au/

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1,122 submissions: 1,075 from the public, 23 from organisations and 24 from public authorities

Object747
Support353
Comment22

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.