Good Earth Green Hydrogen and Ammonia Project
A green hydrogen and ammonia plant on the Gwydir Highway, Moree
Where it is in the process
Approved on 23 Feb 2026
What it proposes
AI summary. Written from this project's page and its GEGHA Project - Assessment Report and GEGHA Project - Development Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A green hydrogen and ammonia plant on the Gwydir Highway, Moree
The project is a green hydrogen and ammonia production and storage facility at 2910 and 2912 Gwydir Highway, about 24 kilometres south-west of Moree in the Moree Plains Shire. It has an estimated development cost of $71 million. It would produce up to 2,200 tonnes a year of hydrogen and 4,500 tonnes a year of ammonia, using power from the adjacent solar farm. It would create up to 60 construction jobs and 10 operational jobs on a site of about 178 ha.
The environmental impact statement was exhibited from 18 Jun 2025 to 15 Jul 2025 and drew 40 submissions, all objecting. The proponent responded in November 2025. The department's assessment found it approvable, focusing on hazards and risk and on water management. A department Executive Director, as the Minister's delegate, approved it on 23 Feb 2026, with conditions. Next, the proponent must meet those conditions, including hazard studies before construction starts.
- Capital investment
- $71MGEGHA Project - Assessment Report
- Hydrogen production limit
- 2,200 tonnes a yearGEGHA Project - Assessment Report
- Ammonia production limit
- 4,500 tonnes a yearGEGHA Project - Assessment Report
- Construction jobs
- 60 jobsGEGHA Project - Assessment Report
- Operational jobs
- 10 jobsGEGHA Project - Assessment Report
- Site area
- 178 haGEGHA Project - Assessment Report
- Hydrogen electrolyser capacity
- 15 MWPortal page
- Public submissions
- 40 submissionsPortal page
The department's description
Construction and operation of a green hydrogen and ammonia production and storage facility, including:
- a 15-megawatt hydrogen electrolyser
- a 16 tonne per day ammonia production plant
- associated storage facilities and site infrastructure
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
40 submissions: 30 from the public and 10 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
80 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition1
Early Consultation2
SEARs4
EIS32
- Appendix A - SEARs and Concordance Table
- Appendix B.1 - Economic Impact Analysis
- Appendix B.10 - Historical Cultural Heritage Memo
- Appendix B.11 - On-site WMP
- Appendix B.12 - Groundwater Drawdown Assessment
- Appendix B.13 - Contaminated Land Assessment
- Appendix B.14 - LUCRA
- Appendix B.15 - Biosecurity Risk Assessment
- Appendix B.16 - Crown Reserves Assessment
- Appendix B.17 - Rehabilitation Plan
- Appendix B.18 - EPBC Self-assessment
- Appendix B.19 - AQIA
- Appendix B.2 - Traffic Impact Assessment
- Appendix B.20 - Initial Fire PS
- Appendix B.3 - Soil and Water Assessment
- Appendix B.4 - Bush Fire Assessment Report
- Appendix B.5 - BDAR Report
- Appendix B.6 - Visual Impact Assessment
- Appendix B.7 - ACHAR_Public Exhibition Copy
- Appendix B.8 - Preliminary Hazard Analysis
- Appendix B.9 - NVIA
- Appendix C - Environmental Risk Assessment
- Appendix D - Detailed maps and plans
- Appendix E - Wathagar Cotton Gin EPL
- Appendix F - Landholder Letter of Authority
- Appendix G - Consultation Record & Plan
- Appendix H - Mosquito Management Plan
- Appendix I - Wathagar Gin Entry Concept Design
- Appendix J - EDC Report_Redacted
- Appendix K - Consolidation of Mitigation Measures
- Application_20250527054624
- GEGHA Project - Environmental Impact Statement
Response to Submissions12
- Appendix A - Submissions Register
- Appendix B - GEGHA Project Updated TIA
- Appendix C - GEGHA Updated ACHAR_redacted
- Appendix D - GEGHA Hazard and Risk Responses
- Appendix E - Supplementary Soil and Water Responses
- Appendix F - GEGHA Updated BDAR
- Appendix G - Hiringa Letter & EPA Response
- Appendix H - GEGHA Hiringa response & updated mapping
- Appendix I - GEGHA Updated Landowners consents
- Appendix J - GEGHA Updated Mitigation Measures
- GEGHA Submissions Report_05.11.25
- Request Submissions Report Letter
Agency Advice18
- EIS - CPHR Advice
- EIS - Crown Lands Advice
- EIS - DCCEEW Water Group Advice
- EIS - DPIRD Agriculture and Biosecurity Advice
- EIS - EPA Advice
- EIS - Essential Energy Advice
- EIS - FRNSW Advice
- EIS - HNELHD Advice
- EIS - HNSW ACH Advice
- EIS - RFS Advice
- EIS - TfNSW Advice
- EIS - WaterNSW Advice
- RTS - CPHR Group Advice
- RTS - Crown Lands Advice
- RTS - DCCEEW Water Group Advice
- RTS - EPA Advice
- RTS - HNSW ACH Advice
- RTS - TfNSW Advice
Determination4
Management Plans and Strategies4
Notifications1
What's near it
Where it is
- Suburb
- Moree
- Council area
- Moree Plains
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.