On the map
State significant development

Glendenning Road Data Centre

A 235 MW data centre at 2 Glendenning Road, Glendenning

Decided: approved on 14 Sep 2026Data centresRegional scale

Where it is in the process

Approved on 14 Sep 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination14 Sep 2026 (done)
  9. Approved14 Sep 2026

What it proposes

AI summary. Written from this project's page and its Signed - SSD Instrument of Consent and Signed - SSD-SSI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 235 MW data centre at 2 Glendenning Road, Glendenning

The project is a data centre at 2 Glendenning Road, Glendenning, in the Blacktown council area, on a 10.44 ha site in the Glendenning Industrial Precinct. It has three buildings of up to five storeys and up to 45.3 m high, with 50,233 m² of floor area, back-up diesel generators, cooling plant and battery rooms. The department gives a capital investment of $2,168,267,746. The consent limits power consumption to 235 MW.

The environmental impact statement (EIS) was exhibited from 16 May 2025 to 12 Jun 2025. It drew 2 submissions: 1 objecting and 1 commenting. The council's objection was about bulk, scale and landscaping. The proponent responded and refined the design. A director of the department, acting for the Minister, approved it on 14 Sep 2026 with conditions. Next, the proponent must meet those conditions, including noise limits and an air quality plan.

Capital investment
$2.17bnSigned - SSD-SSI Assessment Report
Maximum power consumption (consent limit)
235 MWSigned - SSD Instrument of Consent
Maximum building height
45.3 mSigned - SSD-SSI Assessment Report
Total gross floor area
50,233 m²Signed - SSD-SSI Assessment Report
Site area
10.44 haSigned - SSD-SSI Assessment Report
Car parking spaces
165 car spacesSigned - SSD-SSI Assessment Report
New trees to be planted
317 treesSigned - SSD-SSI Assessment Report
Back-up generator operation limit
170 hours a yearSigned - SSD Instrument of Consent

The department's description

Construction and operation of a data centre with a power consumption of 202.4 MW comprising of three, five-storey data centre buildings with a maximum height of 43.2 m, electrical substation, bulk earthworks, car parking and site infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

2 submissions: 1 from organisations and 1 from public authorities

Object1
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

119 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs2
EIS40
Response to Submissions31
Agency Advice25
Additional Information8
Determination3
Management Plans and Strategies7

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.