Gerroa Quarry
Where it is in the process
Approved on 2 Sep 2008
What it proposes
The portal gives no description.
Modifications
3 changes to the project after its decision, each assessed as a case of its own, newest first.
Gerroa Quarry - Gerroa Sand Production Increase (MOD2)MP05_0099-Mod-2
To increase the annual product transport limit at the Quarry from 80,000 tonnes per annum (tpa) to 120,000 tpa
Its 24 documents
24 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application2
Response to Submissions2
Agency Advice13
Additional Information2
Determination4
Mod 1 - Condition ChangesMP05_0099_Mod_1
Mod 1 - Condition ChangesMP05_0099-Mod-1
Its 55 documents
55 documents in 7 folders, each on the NSW Planning Portal
Submissions6
Response to Submissions14
Agency Advice10
Additional Information10
Recommendation3
Determination2
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
24 documents in 9 folders, each on the NSW Planning Portal
Application6
Request for DGRS1
Response to Submissions1
Determination2
Management Plans and Strategies3
Agreements2
Community Consultative Committees and Panels6
Independent Reviews and Audits2
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.