On the map
State significant development

Edderton Solar Farm

A 350 MW solar farm and battery at Edderton Road

Under way: at prepare eisEnergy: solarDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 350 MW solar farm and battery at Edderton Road

The proponent proposes a solar farm with a combined generating capacity of 350 MW, with a battery energy storage system (BESS). It would sit on land at Edderton Road and Denman Road, about 17 km south-south-west of Muswellbrook, mostly in the Muswellbrook Shire and partly in the Singleton Shire. The solar panels would be in three areas, called Mayfield, Bowfield and Plashett. The proponent estimates a development cost of about $850 million and about 800,000 MWh of energy a year.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) were issued and then amended in June 2026. No submissions have been made, because the EIS has not yet been exhibited. Next, the EIS is to be exhibited and the public can make submissions. The department then assesses the project and decides it.

Solar farm capacity
350 MWScoping Report
Estimated development cost
$850MScoping Report
Annual energy generation
800,000 MWhScoping Report
Distance south-south-west of Muswellbrook
17 kmScoping Report

The department's description

Construction and operation of a 350 MW Solar Farm and associated BESS

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.