On the map
State significant development

Eastern Creek Resource Recovery Facility

Decided: approved on 13 Oct 2022Waste

Where it is in the process

Approved on 13 Oct 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination13 Oct 2022 (done)
  9. Approved13 Oct 2022

What it proposes

The department's description

Construction and operation of a resource recovery facility comprising:

- a concrete recycling plant with a processing capacity of 100,000 tonnes per year

- a material storage depot with a capacity of 36,000 tonnes per year

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

10 submissions: 2 from organisations and 8 from public authorities

Object2
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

MOD - 1 - Increase Waste ThroughputSSD-9774-Mod-1

Under way: at response to submissions · 4 submissions

Consolidation of all waste processing operations on Lots 4 & 5 DP 1225803, amendment to size of waste processing shed and increase in waste throughput from 136,000 to 250,000 tonnes per annum.

Its 13 documents

13 documents in 4 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.