On the map
State significant development

Early Works for a Mixed Use Redevelopment at 16-20 Old Castle Hill Road

Early excavation works at 16-20 Old Castle Hill Road, Castle Hill

Decided: approved on 2 Jul 2026HomesLocal scale

Where it is in the process

Approved on 2 Jul 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination2 Jul 2026 (done)
  9. Approved2 Jul 2026

What it proposes

AI summary. Written from this project's page and its SSD Instrument of Consent and SSD-SSI Assessment Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Early excavation works at 16-20 Old Castle Hill Road, Castle Hill

The proponent sought approval for early works at 16-20 Old Castle Hill Road, Castle Hill, in The Hills Shire. The works are site establishment, demolition of all existing structures, remediation, bulk excavation up to about 25 m deep, services work and removal of 75 trees, with 24 retained. The department puts the cost at $13,358,497 and says it would provide 81 construction jobs. It prepares the site for a separate mixed use proposal, which is not part of this approval.

The environmental impact statement (EIS) was exhibited from 27 Feb 2026. It drew 28 submissions: 22 objecting, 1 supporting and 5 commenting. The proponent responded on 1 May 2026 and gave more information on 5 May 2026 and 1 June 2026. The department's Executive Director, acting for the Minister, approved the works with conditions on 2 Jul 2026. Next, the proponent must meet the conditions before and during the works.

Estimated development cost
$13.4MSSD-SSI Assessment Report
Construction jobs
81 jobsSSD-SSI Assessment Report
Maximum excavation depth
25 mSSD-SSI Assessment Report
Trees to be removed
75 treesSSD-SSI Assessment Report
Trees to be retained
24 treesSSD-SSI Assessment Report
Public submissions
28 submissionsPortal page

The department's description

Early works including:

Site establishment

Establishment works and construction activities

Bulk excavation

Piling, shoring walls and capping beams to support structures during construction

Infrastructure services coordination and

Tree removal

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

28 submissions: 26 from the public, 1 from organisations and 1 from public authorities

Object22
Support1
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

62 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs2
EIS27
Response to Submissions8
Agency Advice6
Additional Information11
Determination5
Reports1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.