Early Works - 19A Evans Avenue, Eastlakes
Early works for the Eastlakes Shopping Centre site, Eastlakes
Where it is in the process
Approved on 6 Nov 2026
What it proposes
AI summary. Written from this project's page and its SSD Instrument of Consent and SSD-SSI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Early works for the Eastlakes Shopping Centre site, Eastlakes
The project is early works at 19A Evans Avenue, Eastlakes, in the Bayside Council area, ahead of a separate application for a mixed use development with housing on the site. It includes site establishment, erosion and sediment control, bulk excavation, a piled shoring wall and the lower basement levels. The works would dig up to about 13.79 m deep on a site of 17,960 m². The estimated development cost is $78,331,188, excluding GST.
The environmental impact statement (EIS) was exhibited from 17 Jun 2026 to 1 Jul 2026. The portal records 10 submissions: 3 objecting, 4 supporting and 3 commenting. The proponent responded and gave further information after two requests. The department recommended approval, and its Director approved the project on 6 Nov 2026 as the Minister's delegate, with conditions. Next, the proponent must meet those conditions, including management plans, before works start. The main works are assessed separately.
- Estimated development cost
- $78.3MSSD-SSI Assessment Report
- Site area
- 17,960 m²SSD-SSI Assessment Report
- Maximum excavation depth
- 13.79 mSSD-SSI Assessment Report
The department's description
Earlyworks for Eastlakes Shopping Centre redevelopment, including:
- Site Establishment
- Erosion and sediment control
- Bulk excavation
- Construction and anchoring of piled shoring wall and capping beam
- Infrastructure services coordination
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
10 submissions: 9 from the public and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
74 documents in 9 folders, each on the NSW Planning Portal
Notice of Exhibition1
Early Consultation1
Request for SEARs3
EIS21
- APPENDIX B BDAR Waiver DPHI Letter
- APPENDIX C BDAR Waiver Request
- APPENDIX E- SSD Order 2025
- APPENDIX F - Community Engagement Outcomes Report
- APPENDIX G - Survey Plan
- APPENDIX H - Estimated Development Cost Report
- APPENDIX I - Architectural Plans
- APPENDIX J - Detailed Site Investigation
- APPENDIX K - Sample consultation letter
- APPENDIX L Integrated Water Management Report
- APPENDIX M - Geotechnical Assessment
- APPENDIX N Waste Management Plan
- APPENDIX O Noise and Vibration Assessment
- APPENDIX P Flood Impact Risk Assessment
- APPENDIX S - Heritage and Archaelogical Assessment
- APPENDIX S Aboriginal Cultural Heritage Report
- Appendix B BDAR Waiver Determination
- Appendix B Waiver Determination
- Appendix D - Statutory Compliance Table
- FINAL EIS - Early Works - 19A Evans Avenue, Eastlakes
- SEARs Compliance Table - Appendix A
Response to Submissions17
- Appendix A – Submissions Register (PPUD)
- Appendix B - Architectural Plans (CQ Studio)
- Appendix C - CTMP Issue D (TTPA)
- Appendix D - CTMP Swept Path Analysis extraction (TTPA)
- Appendix E - Asbestos Clearance Cert (EI Australia)
- Appendix F - NVIAMP Rev.D (Paragon)
- Appendix G - DMPlan Rev.F (Katarina David)
- Appendix H - Tree Removal Plan (Redgum Arborist)
- Appendix I - ECSP Rev. B (at&l)
- Appendix J - FIRA Rev.B (ADP)
- Appendix K - Hydrogeologist Memo AIP Rev.1 (Katarina David)
- Appendix L - Dust Management Plan Rev. O (Builtcom)
- Appendix M - WMP Rev.E (Elephants Foot)
- Appendix N - Updated Mitigation Measures (PPUD)
- Appendix O - Dewatering Permit (Bayside Council)
- RTS report_19A EvansAve, Eastlakes
- Request RTS Letter- 19A Evans Avuenue Eastlakes
Agency Advice11
- 20260708 - TfNSW Response
- CPHR Response - 19A Evans Avenue Eastlakes
- Council RTS Response
- Council Submission to EIS - 19A Evans Avenue, Eastlakes
- DCA Technical Advisory Advice - SSD-105575706
- Early Works 19A Evans Avenue, Eastlakes SSD-105575706
- Early works 19A Evans Ave Eastlakes CASA no comments
- Early works 19A Evans Avenue Eastlakes EIS
- MCEF of DCCEEW’s CPHR group SSD-105575706
- SWC Response - SSD-105575706
- Sydney Water DA Info Sheet (For Proponent)
Additional Information11
- 25-1352-EW STORMWATER PACKAGE (26-06-19)
- 2nd Request for Information
- ACE-Confirmation-Letter-G1540-Eastlakes
- Amended basement plans-Eastlakes
- Appendix A - Updated Tree Removal Plan_Eastlakes
- REP004-01-25-1352 SSDA Earlyworks FIRA
- RTS Response
- Response to Further RFI_ Amended Proposed Works
- Slab Dimension Architectural Plans
- Superseded Appendix H - Tree Removal Plan
- Updated Engineering Advice with data
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.