On the map
Part 4 development

Donaldson Coal Mine

Decided: approvedMining

Where it is in the process

Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Pit ExtensionDA98/01173-Mod-1

Decided: approved by the Planning Assessment Commission

Its 3 documents

3 documents in 1 folder, each on the NSW Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 2 - Mine Life ExtensionDA98/01173-Mod-2

Decided: approved on 24 Jun 2011 by the department (deputy director-general)

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Submissions5

See the 5 documents on the Planning Portal

Assessment3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

6 documents in 1 folder, each on the NSW Planning Portal

Reports6

See the 6 documents on the Planning Portal

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.