Corrimal Coke Works – Stage 2-4 Early Stage (Civil Works)

Civil works and parks at the Corrimal Coke Works, Corrimal

Decided: approved on 17 Aug 2026HomesLocal scale

Where it is in the process

Approved on 17 Aug 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination17 Aug 2026 (done)
  9. Approved17 Aug 2026

What it proposes

AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Civil works and parks at the Corrimal Coke Works, Corrimal

The project is the civil works for stages 2 to 4 of the former Corrimal Coke Works site at 27 Railway Street, Corrimal, in the Wollongong City Council area. It includes local roads, drainage and stormwater, public domain works, Central Park of about 3,000 m² and Southern Park of about 11,500 m², and a shared pedestrian and cycle path. A subdivision would create nine residential lots. The capital investment is $10,812,082, with 350 construction jobs and 10 operational jobs.

The environmental impact statement (EIS) was exhibited from 27 Feb 2026 and drew 3 submissions: 1 objecting and 2 commenting. The proponent responded on 21 May 2026. The department recommended approval, and a director of the department, acting for the Minister, approved it on 17 Aug 2026, with conditions. Next, the proponent must meet those conditions, including heritage, flooding and stormwater requirements, before work starts.

Capital investment
$10.8MAssessment Report
Construction jobs
350 jobsAssessment Report
Operational jobs
10 jobsAssessment Report
New residential lots
9 lotsAssessment Report
Southern Park area
11,500 m²Assessment Report
Central Park area
3,000 m²Assessment Report
Site area for the civil works
66,226 m²Assessment Report

The department's description

Civil Works to support the Corrimal Stage 2-4 Built Form SSDA (SSD-83789711). The 'facilitating' civil works package to include the Central Park, Southern Park, roads, drainage, stormwater, and subdivision.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

3 submissions: 1 from the public, 1 from organisations and 1 from public authorities

Object1
Support0
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

96 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation2
Request for SEARs1
SEARs2
EIS33
Response to Submissions20
Agency Advice17
Additional Information16
Determination4

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.