On the map
State significant development

Coonerang Wind Farm

Coonerang Wind Farm, off the Snowy Mountains Highway

Under way: at prepare eisEnergy: windDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Coonerang Wind Farm, off the Snowy Mountains Highway

The proponent proposes a wind farm with battery storage, about 11 km south-east of Cooma and 8.5 km north-west of Nimmitabel, in the Snowy Monaro Regional Council area. The portal describes up to 34 turbines. The scoping report describes about 25 turbines with a combined capacity of up to about 150 MW and a 100 MW / 400 MWh battery, on land of about 6,713 ha. Its concept layout shows 34 possible turbine sites, to be cut to about 25. No capital investment figure is stated.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). The scoping report was prepared in August 2023 and the Secretary's environmental assessment requirements (SEARs) have been issued. No submissions have been made yet. Next, the proponent lodges the EIS, which is then exhibited so the public can make submissions, before the department assesses the project.

Wind turbines (portal description)
34 turbinesPortal page
Wind farm capacity
150 MWScoping Report
Battery capacity
100 MWScoping Report
Battery storage
400 MWhScoping Report
Subject land area
6,713 haScoping Report
Turbine tip height
266 mScoping Report

The department's description

Construction and operation of a wind farm with up to 34 wind turbines, battery storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.