Concept & Stage 1- ANZAC Village Seniors Housing
Where it is in the process
At assessment
What it proposes
The department's description
Concept & Stage 1 for new ILUs and new RAC beds
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
164 submissions: 162 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
107 documents in 5 folders, each on the NSW Planning Portal
Notice of Exhibition1
SEARs1
EIS55
- Appendix A - SEARs Compliance Table
- Appendix AA- Flood Impact Risk Assessment
- Appendix B - Statutory Compliance Table
- Appendix BB- Bushfire Report
- Appendix C - Summary of Mitigation Measures
- Appendix CC- Aboriginal Cultural Assessment Report
- Appendix D - Clause 4.6 Variation Request - Schedule 4
- Appendix DD- Statement of Heritage Impact
- Appendix E- Engagement Outcomes Report
- Appendix EE- Heritage Conservation Management Plan
- Appendix F - Design Report and Indicative Reference Scheme
- Appendix FF- Hydraulic, Electrical and Communications
- Appendix G - Concept Envelope Drawings for approval
- Appendix GG- Pedestrican Wind Assessment
- Appendix H - Stage 1 Architectural Drawings
- Appendix HH- BCA Compliance Letter
- Appendix I- Site Survey
- Appendix II- Accessibility Design Review Report
- Appendix J - Design Verification Statement
- Appendix JJ- Crime Prevention Through Environmental Design
- Appendix K- Visual Impact Assessment
- Appendix KK- Preliminary Construction Management Plan
- Appendix L- Transport Impact Assessment
- Appendix LL- Geotechnical Assesment Stage 1
- Appendix M- Noise and Vibration Impact Assessment
- Appendix MM- Preliminary Site Assessment
- Appendix N- IWMP and Civil Design Report
- Appendix NN- Surface and Groundwater Impact Assessment
- Appendix O- Geotechnical Report Masterplan
- Appendix OO- Groundwater Impact Asessment
- Appendix P- Stage 1 Bulk Earthworks and Civil Package
- Appendix PP- Groundwater Quality Screening
- Appendix Q- Preliminary Acid Sulfate Soils Management Plan
- Appendix QQ- Sampling Analysis and Quality Plan for DSI
- Appendix R- Detailed Site Investigation
- Appendix RR- Stage 1 Qualitative Natural Ventilation Study
- Appendix S- Remediation Action Plan
- Appendix SS- Social Impact Assessment
- Appendix T- Concept Landscape Design Report
- Appendix TT- ESD Report Stage 1
- Appendix U - Stage 1 Landscape Plans and Report
- Appendix UU- Stage 1 Section J (JV3) Report
- Appendix V- Arboricultural Impact Assessment
- Appendix VV - BASIX and NatHERS Certificates
- Appendix W- ESD Report Masterplan
- Appendix WW- Hazards Analysis
- Appendix X- Biodiversity Development Assessment Report
- Appendix XX- Seniors Housing Design Guide Compliance Table
- Appendix Y- Demolition and CWMP
- Appendix YY- Apartment Design Guide Compliance Table
- Appendix Z - Operational Waste Management Plan
- Appendix ZZ - Housing SEPP Schedules Compliance Table
- Environmental Impact Statement - ANZAC Village
- Under Separate Cover - EDC Masterplan Cover Letter
- Under Separate Cover - EDC Stage 1 Cover Letter
Response to Submissions35
- Appendix A - Feedback Recieved
- Appendix A - Submissions Register
- Appendix B - Response to Submissions Table_16.09.26
- Appendix C - Architectural Detailed Response to Submissions
- Appendix D - Updated PCMP
- Appendix E - Revised Concept Masterplan Envelope Drawings
- Appendix F - Revised Stage 1 Drawings for approval
- Appendix G - Revised Stage 1 Landscape Design Report
- Appendix H - Revised Stage 1 Landscape Drawings
- Appendix I - Afflux (Appendix E of FIRA)
- Appendix I - Design (Appendix C of FIRA)
- Appendix I - Design (Appendix D of FIRA)
- Appendix I - Existing (Appendix B of FIRA)
- Appendix I - Revised Flood Impact Risk Assessment
- Appendix K - Updated TAIA
- Appendix L - Traffic RFI Statement
- Appendix M - Updated Noise and Vibration Assessment
- Appendix N - IWMP and Civil Design Report
- Appendix O - Geotechnical Opinion Letter
- Appendix P - Stage 1 Earthworks and Civil Plans
- Appendix Q - Updated Operational Waste Management Plan
- Appendix R - Updated BCA Compliance Letter
- Appendix S - Accessibility Statement
- Appendix T - Updated Stage 1 ESD Report
- Appendix U - BASIX Certificate - ILUs
- Appendix U - BASIX Certificate - Townhouses
- Appendix U - BASIX Summary Report - ILUs
- Appendix U - BASIX Summary Report - Townhouses
- Appendix U - NatHERS Group Certificate - ILUs
- Appendix U - NatHERS Group Certificate - Townhouses
- Appendix U - Section J Compliance Letter
- Appendix U - Section J Report
- Appendix U - Stamped Drawings
- Request RTS Letter
- Response to Submissions Report_16.09.26
Agency Advice15
- ANZAC Village Seniors Housing SSD-85869467
- CPHR Response - SSD-85869467
- Councils Submission - Anzac Village Seniors Housing
- DCCEEW Water Group - Concept & Stage 1- ANZAC Village Seniors Housing
- FRNSW- Concept and S1 ANZAC Village Seniors Housing
- HNSW ACH - EIS - SSD-85869467
- NSW RFS - EIS
- NSW SES Response ANZAC Village Seniors Housing
- RTS Advice - DCA Technical Advisory Advice SSD-85869467
- RTS Advice - Northern Beaches Council
- RTS Advice - TfNSW - SYD25-00686-03
- RTS advice - SES - ANZAC Village Seniors Housing SSD-85869467
- RtS Advice - MCEF - SSD-85869467
- Sydney Water Response - SSD-85869467
- TfNSW Response for SSD-85869467 - EIS
What's near it
Where it is
- Suburb
- Narrabeen
- Council area
- Northern Beaches
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.