Approved on 28 Feb 2019

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination28 Feb 2019 (done)
  9. Approved28 Feb 2019

What it proposes

The department's description

Expansion of the Coffs Harbour Hospital

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 12 from organisations

Object0
Support0
Comment12

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

Coffs Harbour Hospital Expan MOD 5 - RainwaterSSD-8981-Mod-5

Decided: approved on 12 May 2021 by the department (director)

Deletion of conditions B27 and D21 requiring the implementation of a rainwater harvesting system.

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Coffs Harbour Hospital Expan MOD 4 - Car parkingSSD-8981-Mod-4

Decided: approved on 24 Sep 2020 by the department (director)

Amend condition B31 to the total parking space requirement from to 1,133 to 1,128.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Coffs Harbour Hospital Expan MOD 3 - Solar panelsSSD-8981-Mod-3

Decided: approved on 28 Jul 2020 by the department (director)

Installation of solar panels in Western Carpark.

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Coffs Harbour Hospital Expn MOD 2 - Design changesSSD-8981-Mod-2

Decided: approved on 1 Dec 2019 by the department (director)

Minor facade design refinements, new staging conditions, deletion of conditions B15 and B16 relating to flood protection, extension of construction hours on Saturdays until 4pm and change to approval authority for disposal of rainwater/seepage.

Its 6 documents

6 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Coffs Harbour Hospital Expan MOD 1 - Car parkingSSD-8981-Mod-1

Decided: approved on 25 Aug 2019 by the department (director)

Modify condition D12 which requires additional parking to be provided within the Coffs Harbour Hospital Campus prior to the commencement of the operation of the approved works.

Its 32 documents

32 documents in 5 folders, each on the NSW Planning Portal

Early Consultation13

See the 13 documents on the Planning Portal

Modification Application14

See the 14 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.