CLARA Energy Project Rosedale
A green hydrogen plant with a 250 MW solar farm, Mundarlo
Where it is in the process
At prepare eis
What it proposes
AI summary. Written from this project's page and its ROS-ARC-RPT-EPA-001-Scoping Report_Draft 6.0 on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A green hydrogen plant with a 250 MW solar farm, Mundarlo
The proponent proposes a green hydrogen production facility at 232 Rosedale Road, Mundarlo, in the Cootamundra-Gundagai Regional Council area, along the Hume Highway. Hydrogen would be made by electrolysers powered by an on-site solar farm with a capacity of 250 MW, producing 25 tonnes a day. The facility would also have hydrogen liquefaction, compression, storage and wholesale distribution, a water treatment plant and a supplementary power supply. The site is about 5366 ha and the project area about 1074 ha. No capital investment or job numbers are stated.
The case is at the stage where the proponent prepares its environmental impact statement (EIS). The scoping report is dated July 2023, and the Secretary's environmental assessment requirements (SEARs) have been issued. Next, the EIS is to be exhibited and the public can make submissions. No submissions have been made so far. The department then assesses the project before a decision.
- Solar farm capacity
- 250 MWROS-ARC-RPT-EPA-001-Scoping Report_Draft 6.0
- Hydrogen production
- 25 tonnes a dayROS-ARC-RPT-EPA-001-Scoping Report_Draft 6.0
- Site area
- 5,366 haROS-ARC-RPT-EPA-001-Scoping Report_Draft 6.0
- Project area
- 1,074 haROS-ARC-RPT-EPA-001-Scoping Report_Draft 6.0
The department's description
Construction and operation of a green hydrogen production facility, comprised of:
- hydrogen production, liquefaction, compression, storage and wholesale distribution
- 250MW solar farm
- water treatment plant
- supplementary power supply
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
7 documents in 2 folders, each on the NSW Planning Portal
Request for SEARs1
What's near it
Where it is
- Suburb
- Mundarlo
- Council area
- Cootamundra-Gundagai Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.